Permit Reviews

Permit Number - T18CM04277
Permit Status: C of o
Permit Description: RESTAURANT
Start Date Submittal Complete Date Status  
02/21/2019 REVISION - - 1ST 02/21/2019 COMPLETED Review Details
02/25/2019 REVISION - - 1ST 03/19/2019 COMPLETED Review Details
06/01/2018 PLANS OK TO SUBMIT - COMM 06/04/2018 COMPLETED Review Details
06/11/2018 COMMERCIAL - NEW 07/16/2018 COMPLETED Review Details
10/26/2018 RESUBMITTAL - TI ALL 11/28/2018 COMPLETED Review Details
11/29/2018 RESUBMITTAL 01/14/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T18CM04277
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
06/01/2018 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T18CM04277
Permit Description: RESTAURANT
Total Completed Inspections - 36
Date Description Inspector Results Comments
11/09/2018 MECHANICAL - FINAL RSHERRY Approved AIR BALANCE REPORT REQUIRED
11/29/2018 PLUMBING - FINAL RSHERRY Approved WATER DISINFECTION REPORT REQUIRED
02/01/2019 ELECTRIC - CONSTRUCTION POWER RCAMACHO Approved TMPP
02/07/2019 PLUMBING - ROUGH, SOIL MHASSAN Approved
02/20/2019 ELECTRIC - UFER MHASSAN Approved
02/27/2019 EXCAVATION/LAYOUT REBAR & ZON MHASSAN Approved Stemwall OK
03/06/2019 BUILDING PRE-SLAB RCAMACHO Approved
03/14/2019 PLUMBING - YARD WTR LINE/TEST RCAMACHO Approved
03/21/2019 SITE - SEWER MHASSAN Approved
04/04/2019 MECHANICAL - INTERMEDIATE MHASSAN Approved
04/04/2019 PLUMBING - INTERMEDIATE MHASSAN Approved
04/04/2019 EXT METAL CLIPS/EXT SHEATHING MHASSAN Approved
04/09/2019 PLUMBING - ROOF DRAINS RCAMACHO Approved
04/18/2019 ELECTRIC - INTERMEDIATE RCAMACHO Approved
04/18/2019 FRAMING RCAMACHO Approved
04/18/2019 STUCCO MESH RCAMACHO Approved
04/23/2019 SHEET ROCK NAILING RCAMACHO Approved
05/09/2019 BUILDING ABOVE CEILING MHASSAN Approved several ceiling wires hanging down finish securing them to the grid.
05/09/2019 MECHANICAL - ABOVE CEILING MHASSAN Approved several ceiling wires hanging down finish securing them to the grid.
05/09/2019 ELECTRIC - ABOVE CEILING MHASSAN Approved Double check the starting point for the upsizing from 2 inch to 4 inch on the venting system. The detail is not real clear but I believe the entire vertical should be 4 inch
05/09/2019 PLUMBING - PROGRESS MHASSAN Approved
05/23/2019 TEP CLEARANCE - AM MHASSAN Approved CODE ECO
06/06/2019 FIRE - FINAL MRoss Approved
06/06/2019 PLUMBING - BACK WATER VALVE RCAMACHO Approved
06/06/2019 OUTDOOR LIGHTING FINAL RCAMACHO Approved APPROVED PER 2090 APPROVAL
06/06/2019 ELECTRIC - OUTDOOR LIGHTING RCAMACHO Approved APPROVED UPON 2090 APPROVAL
06/06/2019 ELECTRIC - FINAL RCAMACHO Approved
06/06/2019 TEP CLEARANCE - PM RCAMACHO Approved CODE TMPP
06/06/2019 ELECTRIC - TEMPORARY SERVICE RCAMACHO Approved TMPP
06/06/2019 ELECTRIC - UNDERGROUND RCAMACHO Approved
06/06/2019 U VALUE FOR WINDOW RCAMACHO Approved
06/06/2019 ROOF NAILING RCAMACHO Approved
06/07/2019 HEALTH DEPT - FINAL 724-7908 PRISCILLAU Approved
06/13/2019 CERTIFICATE OF OCCUPANCY BBENEDON Approved PER ENGINIEERING FINAL
06/13/2019 BUILDING - FINAL BBENEDON Approved PER ENGINNEERING FINAINALS
06/13/2019 ENGINEERING - FINAL BBENEDON Approved APPROVED PER DP18-0138