Permit: T18CM03871
Permit Details
Apply Date:
05/18/2018
Applicant:
JEFFREY ADRAGNA
Description:
WAREHOUSE
Architects:
- PAUL BISHOP
Contractors:
- INDEVCO CONSTRUCTION INC
Permit Reviews
Permit Number - T18CM03871
Permit Status: C of o
Permit Description: WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/26/2019 | REVISION - - 1ST | 02/26/2019 | COMPLETED |
| 02/26/2019 | REVISION - - 1ST | 03/07/2019 | COMPLETED |
| 05/18/2018 | PLANS OK TO SUBMIT - COMM | 05/18/2018 | COMPLETED |
| 05/18/2018 | COMMERCIAL - TI | 06/20/2018 | COMPLETED |
| 10/04/2018 | COMMERCIAL - TI | 10/18/2018 | COMPLETED |
| 10/18/2018 | RESUBMITTAL | 11/21/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM03871
Permit Status: C of o
Permit Description: WAREHOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/18/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM03871
Permit Description: WAREHOUSE
Total Completed Inspections - 34
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/11/2019 | BUILDING PRE-SLAB | MHASSAN | Approved | keep report and photos on column pour backs |
| 04/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN | Approved | |
| 06/25/2019 | ELECTRIC - UNDERGROUND | AKLEINSORGE | Approved | 3 floor outlets in front showroom |
| 06/25/2019 | PLUMBING - ROUGH, SOIL | AKLEINSORGE | Approved | Red lined floor drain in front showroom |
| 06/25/2019 | PLUMBING - PRE SLAB | AKLEINSORGE | Approved | Front showroom plumbing trench, ok for concrete placement |
| 07/01/2019 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN | Approved | approval is for training house within the building. |
| 07/01/2019 | ROOF NAILING | MHASSAN | Approved | approval is for training house within the building. |
| 07/16/2019 | PLUMBING - PROGRESS | MHASSAN | Approved | |
| 07/16/2019 | ELECTRIC - PROGRESS | MHASSAN | Approved | |
| 07/16/2019 | MECHANICAL - INTERMEDIATE | MHASSAN | Approved | |
| 07/16/2019 | BUILDING - PROGRESS | MHASSAN | Approved | |
| 07/16/2019 | FRAMING | MHASSAN | Approved | |
| 08/12/2019 | GAS CLEARANCE | AKLEINSORGE | Approved | |
| 08/12/2019 | PLUMBING - GAS PRESSURE TEST | AKLEINSORGE | Approved | Clear gas |
| 08/19/2019 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | |
| 10/17/2019 | ELECTRIC - SERVICE UPGRADE | DMUNIZ | Approved | Clear TEP (INCR). |
| 10/17/2019 | ELECTRIC - UFER | DMUNIZ | Approved | |
| 10/18/2019 | TEP CLEARANCE - AM | DMUNIZ | Approved | CODE INCR |
| 11/14/2019 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Submit plumbing letterhead for concealed areas. |
| 11/14/2019 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 11/14/2019 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | |
| 11/14/2019 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | |
| 11/14/2019 | BUILDING ABOVE CEILING | ESTEVENS | Approved | |
| 11/18/2019 | ENGINEERING - FINAL | RLEDONNE | Approved | complete work on approved plan. PageA three pertaining to ADA parking and pathway. |
| 12/20/2019 | MECHANICAL - FINAL | TVALENCIA | Approved | |
| 12/20/2019 | PLUMBING - FINAL | TVALENCIA | Approved | |
| 12/20/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 12/20/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 12/20/2019 | ELECTRIC - OUTDOOR LIGHTING | TVALENCIA | Approved | |
| 12/20/2019 | FIRE - FINAL | gsereno1 | Approved | Trying to get TCO. Shall have ceiling tiles in and monitoring available. |
| 01/27/2020 | PLUMBING - GAS PRESS TEST FNL | TVALENCIA | Approved | 1- Gas meter is on. |
| 01/31/2020 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
| 02/25/2020 | ZONING - FINAL | BBENEDON | Approved | |
| 03/27/2020 | BUILDING - FINAL | TVALENCIA | Approved | PER RSHERRY NO AIR BALANCE OR CHLORONATION REPORT REQUIRED |