Permit: T18CM03744
Permit Details
Status:
L of c
Type:
COMMERCIAL ADDITION
Address:
626 N CRAYCROFT RD
Address NEW:
626 N CRAYCROFT RD
Apply Date:
05/15/2018
Applicant:
N/A
Description:
TI: OFFICES / ADDITION: CANOPY
Architects:
- JOHN B RIGGS
Contractors:
- MURRAY BUILDERS LLC
Permit Reviews
Permit Number - T18CM03744
Permit Status: L of c
Permit Description: TI: OFFICES / ADDITION: CANOPY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/15/2018 | PLANS OK TO SUBMIT - COMM | 05/15/2018 | COMPLETED |
| 05/15/2018 | COMMERCIAL - TI | 06/25/2018 | COMPLETED |
| 06/25/2018 | RESUBMITTAL | 07/06/2018 | COMPLETED |
| 07/05/2018 | RESUBMITTAL | 07/10/2018 | COMPLETED |
| 09/17/2018 | REVISION - - 1ST | 09/17/2018 | COMPLETED |
| 11/30/2018 | REVISION - - 2ND | 11/30/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM03744
Permit Status: L of c
Permit Description: TI: OFFICES / ADDITION: CANOPY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/15/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM03744
Permit Description: TI: OFFICES / ADDITION: CANOPY
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/24/2018 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | ENTRYWAY ROOF BEAM SUPPORT WALL FOOTING OK TO POUR. |
| 08/31/2018 | BUILDING - PROGRESS | BJONES | Approved | 7 COURSES ENTRY ROOF SUPPORT. #5 BAR AT24" OC, DURA WALL EVERY 3 COURSES |
| 08/31/2018 | BUILDING - PROGRESS | BJONES1 | Approved | IVRS - Inspection :* |
| 09/05/2018 | REINFORCED MASONRY PRE-GROUT | GWest | Approved | Final lift of 10", steel 24" vert and 2 horizontal at top-bond beam. |
| 09/26/2018 | ELECTRIC - INTERMEDIATE | MHASSAN | Approved | Please add electrical intermediate to this permit and approve it. |
| 09/26/2018 | PLUMBING - ROUGH, SOIL | MHASSAN | Approved | Please add electrical intermediate to this permit and approve it. Thanks |
| 09/26/2018 | ELECTRIC - PROGRESS | MHASSAN | Approved | |
| 09/26/2018 | FRAMING | MHASSAN | Approved | |
| 10/03/2018 | PLUMBING - PROGRESS | MHASSAN | Approved | |
| 10/03/2018 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | Please add 3035 and approve it. Please add 1025 and partially approve it, add H25 Clips at Lobby entrance canopy. |
| 10/16/2018 | STUCCO MESH | MHASSAN | Approved | |
| 11/07/2018 | PLUMBING - ABOVE CEILING | MHASSAN | Approved | |
| 11/15/2018 | MECHANICAL - ABOVE CEILING | GWEST | Approved | |
| 11/15/2018 | ELECTRIC - ABOVE CEILING | GWEST | Approved | |
| 11/29/2018 | ELECTRIC - SERVICE UPGRADE | GWEST | Approved | |
| 11/30/2018 | TEP CLEARANCE - AM | GWEST | Approved | INCR |
| 12/13/2018 | ZONING - FINAL | RLEDONNE | Approved | Complete all parking on east side of building including Ada. And for final call in development package dp18-0001. |
| 12/14/2018 | BUILDING ABOVE CEILING | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | BUILDING - TEMP POWER FOR TEST | GWEST | Approved | APPROVED PER BUILDIGN FINAL |
| 12/14/2018 | EXT METAL CLIPS/EXT SHEATHING | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | ELECTRIC - SERVICE RELOCATION | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | ELECTRIC - CABLE DROP | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | ELECTRIC - CONSTRUCTION POWER | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | ELECTRIC - UFER | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | ELECTRIC - UNDERGROUND | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | SHEET ROCK NAILING | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | U VALUE FOR WINDOW | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | MECHANICAL - INTERMEDIATE | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/14/2018 | PLUMBING - GAS PRESSURE TEST | GWEST | Approved | |
| 12/14/2018 | ELECTRIC - OUTDOOR LIGHTING | GWEST | Approved | |
| 12/14/2018 | ELECTRIC - FINAL | GWEST | Approved | |
| 12/14/2018 | BUILDING - FINAL | GWEST | Approved | |
| 12/14/2018 | FIRE - FINAL | jvincent | Approved | -add lock box or key switch for gate on west side. APPROVED TO OBTAIN TCO FOR FULL OCCUPANCY Wayne 777-5240 |
| 12/17/2018 | GAS CLEARANCE | GWEST | Approved | |
| 12/17/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 12/17/2018 | PLUMBING - YARD WTR LINE/TEST | GWEST | Approved | APPROVED PER BUILDING FINAL |
| 12/17/2018 | PLUMBING - FINAL | AQUIROZ | Approved | WATER CHLORINATION REPORT REVIEW COMPLETE |