Permit: T18CM02827
Permit Details
Apply Date:
04/17/2018
Applicant:
URBAN ENERGY SOLUTIONS INC ***APA***
Description:
ELECTRONIC REVIEW - INSTALL COMMERCIAL PV SYSTEM
Permit Reviews
Permit Number - T18CM02827
Permit Status: L of c
Permit Description: ELECTRONIC REVIEW - INSTALL COMMERCIAL PV SYSTEM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/17/2018 | WALK THRU - COMM | 05/15/2018 | COMPLETED |
| 05/21/2018 | RESUBMITTAL | 05/21/2018 | COMPLETED |
| 08/01/2018 | REVISION - - 1ST | 08/17/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02827
Permit Status: L of c
Permit Description: ELECTRONIC REVIEW - INSTALL COMMERCIAL PV SYSTEM
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/17/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T18CM02827
Permit Description: ELECTRONIC REVIEW - INSTALL COMMERCIAL PV SYSTEM
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/10/2018 | ELECTRIC - PROGRESS | ESTEVENS | Approved | TEP code is DGC/DGL |
| 12/27/2018 | ELECTRIC - FINAL | DMCCARTHY | Approved | DGC. Meter is metal tagged with address as shown above with the ZIP Code Electric clearance OK to set solar meter and energize commercial system school related. ZIP Code 85719 Food service warehouse for school Two large solar arrays framed with structural steel and purlins |
| 12/27/2018 | OUTDOOR LIGHTING FINAL | DMCCARTHY | Approved | |
| 12/27/2018 | ELECTRIC - OUTDOOR LIGHTING | DMCCARTHY | Approved | |
| 12/27/2018 | ELECTRIC - INTERMEDIATE | DMCCARTHY | Approved | |
| 12/27/2018 | ELECTRIC - UNDERGROUND | DMCCARTHY | Approved | |
| 12/27/2018 | ELECTRIC - UFER | DMCCARTHY | Approved | |
| 12/27/2018 | BUILDING - FINAL | DMCCARTHY | Approved | |
| 12/27/2018 | FRAMING | DMCCARTHY | Approved | |
| 12/27/2018 | ROOF NAILING | DMCCARTHY | Approved | |
| 12/27/2018 | EXCAVATION/LAYOUT REBAR & ZON | DMCCARTHY | Approved | |
| 12/28/2018 | TEP CLEARANCE - AM | DMCCARTHY | Approved | DGC |