Permit: T18CM02367
Permit Details
Apply Date:
03/29/2018
Applicant:
METRO TED LISA
Description:
ADDITION: ADMIN + TI: REMODEL
Contractors:
- CONCORD GENERAL CONTRACTING INC
Permit Reviews
Permit Number - T18CM02367
Permit Status: C of o
Permit Description: ADDITION: ADMIN + TI: REMODEL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/29/2018 | COMMERCIAL - TI | 04/03/2018 | COMPLETED |
04/03/2018 | COMMERCIAL - TI | 05/18/2018 | COMPLETED |
05/18/2018 | RESUBMITTAL - TI ALL | 06/19/2018 | COMPLETED |
06/19/2018 | RESUBMITTAL | 06/25/2018 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM02367
Permit Description: ADDITION: ADMIN + TI: REMODEL
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | TVALENCIA | Approved | |
12/20/2018 | BUILDING PRE-SLAB | JBURGE | Approved | Ok to place concrete. |
05/06/2019 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
07/11/2019 | MECHANICAL - INTERMEDIATE | GWEST | Approved | Upstairs and downstairs addition. And Back of building upstairs and downstairs, conference room, and sales room |
07/11/2019 | MECHANICAL - ABOVE CEILING | GWEST | Approved | Upstairs and downstairs addition. And Back of building upstairs and downstairs, conference room, and sales room |
07/11/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | Upstairs and downstairs addition. And Back of building upstairs and downstairs, conference room, and sales room |
07/11/2019 | ELECTRIC - PROGRESS | GWEST | Approved | |
07/11/2019 | ELECTRIC - ABOVE CEILING | GWEST | Approved | Upstairs and downstairs addition. And Back of building upstairs and downstairs, conference room, and sales room |
07/22/2019 | PLUMBING - PROGRESS | ESTEVENS | Approved | Hospitality sink, supply and drain lines. Condensate line above sales office and addition. |
07/22/2019 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | Hospitality sink, supply and drain lines. Condensate line above sales office and addition. |
08/09/2019 | ELECTRIC - UNDERGROUND | DQUINN | Approved | Ok to pour east parking lot light pole base. Rebar and ufer ok. |
10/29/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
10/29/2019 | FIRE - FINAL | gsereno1 | Approved | |
10/29/2019 | FIRE SPKLR - FINAL | gsereno1 | Approved | |
10/31/2019 | PLUMBING - FINAL | DQUINN | Approved | |
10/31/2019 | MECHANICAL - FINAL | DQUINN | Approved | |
10/31/2019 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
10/31/2019 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
10/31/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
10/31/2019 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
10/31/2019 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | |
10/31/2019 | STEM WALL/RETAINING WALL | DQUINN | Approved | |
10/31/2019 | ROOF NAILING | DQUINN | Approved | |
10/31/2019 | BUILDING ABOVE CEILING | DQUINN | Approved | |
10/31/2019 | FRAMING | DQUINN | Approved | |
10/31/2019 | BUILDING - PROGRESS | DQUINN | Approved | |
10/31/2019 | U VALUE FOR WINDOW | DQUINN | Approved | |
10/31/2019 | BUILDING - FINAL | DQUINN | Approved | APPROVED BY INSPECTOR, AWAITING SPECIAL INSPECTION CERTIFICATES |