Permit: T18CM02242
Permit Details
Apply Date:
03/26/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: RESTAURANT - TCO: FULL BUSINESS OPERATIONS
Architects:
- LOOKER, JEFF ANTHONY
Contractors:
- EQUITEAM LLC
Permit Reviews
Permit Number - T18CM02242
Permit Status: Expired
Permit Description: TI: RESTAURANT - TCO: FULL BUSINESS OPERATIONS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/26/2018 | PLANS OK TO SUBMIT - COMM | 03/28/2018 | COMPLETED |
| 03/29/2018 | 3RD PARTY REVIEW - COMMERCIAL TI | 04/06/2018 | COMPLETED |
| 04/04/2018 | COMMERCIAL - TI | 06/06/2018 | COMPLETED |
| 06/06/2018 | RESUBMITTAL | 06/13/2018 | COMPLETED |
| 06/13/2018 | RESUBMITTAL | 08/08/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02242
Permit Status: Expired
Permit Description: TI: RESTAURANT - TCO: FULL BUSINESS OPERATIONS
Total Outstanding Activity Conditions - 3
| Date | Name |
|---|---|
| 03/26/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 06/08/2018 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
| 06/08/2018 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T18CM02242
Permite Description: TI: RESTAURANT - TCO: FULL BUSINESS OPERATIONS
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| BUILDING ABOVE CEILING | N/A | Not Inspected | ||
| PLUMBING - PROGRESS | N/A | Not Inspected | ||
| 01/11/2019 | FIRE - KITCHEN EXH HOOD FINAL | N/A | Partial Approval | trip test approved. changed nozzles over fryers to correct nozzles. waiting on as builts only. |
| 09/20/2018 | PLUMBING - ROUGH, SOIL | N/A | Partial Approval | INTERIOR GREASE PVC OK TO BACK DOOR. OK TO BACKFILL. |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM02242
Permit Description: TI: RESTAURANT - TCO: FULL BUSINESS OPERATIONS
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/11/2018 | SITE - SEWER | DQUINN | Approved | |
| 10/11/2018 | SITE - SEWER | DQUINN | Approved | All exterior rough pvc ok to backfill |
| 10/16/2018 | FRAMING | BJONES | Approved | contractor asked to add nails to facia in rear of building |
| 10/16/2018 | ROOF NAILING | BJONES | Approved | |
| 10/16/2018 | EXT METAL CLIPS/EXT SHEATHING | BJONES | Approved | |
| 10/19/2018 | PLUMBING - GAS PRESSURE TEST | MHASSAN | Approved | |
| 10/19/2018 | PLUMBING - INTERMEDIATE | MHASSAN | Approved | |
| 10/22/2018 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
| 10/22/2018 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 10/22/2018 | PLUMBING - ABOVE CEILING | DQUINN | Approved | |
| 10/22/2018 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | |
| 10/26/2018 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 10/26/2018 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
| 11/14/2018 | ELECTRIC - UFER | DQUINN | Approved | |
| 11/14/2018 | STUCCO MESH | DQUINN | Approved | |
| 11/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | DMCCARTHY | Approved | Wrong inspections called in 3075 |
| 11/19/2018 | ELECTRIC - UNDERGROUND | DMCCARTHY | Approved | |
| 12/24/2018 | MECHANICAL - FINAL | DMCCARTHY | Approved | need air balance report This inspection should be for building final also however building final not ready still have demoed flat work on the outside and too much debris and stuff inside to do a thorough inspection |
| 12/24/2018 | PLUMBING - FINAL | DMCCARTHY | Approved | |
| 12/24/2018 | ELECTRIC - FINAL | DMCCARTHY | Approved | building is cluttered with stuff equipment appliances and construction debris |
| 01/04/2019 | GAS CLEARANCE | RCHANDLER | Approved | |
| 01/09/2019 | OUTDOOR LIGHTING FINAL | RCHANDLER | Approved | |
| 01/09/2019 | BUILDING - FINAL | RCHANDLER | Approved |