Permit: T18CM02106
Permit Details
Apply Date:
03/21/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RESTROOM ADDITION
Contractors:
- AVANGUARD GENERAL CONTRACTING L L C
Permit Reviews
Permit Number - T18CM02106
Permit Status: Expired
Permit Description: RESTROOM ADDITION
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/21/2018 | PLANS OK TO SUBMIT - COMM | 03/26/2018 | COMPLETED |
03/23/2018 | COMMERCIAL - TI | 05/10/2018 | COMPLETED |
05/10/2018 | RESUBMITTAL | 05/11/2018 | COMPLETED |
05/18/2018 | RESUBMITTAL | 05/23/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM02106
Permit Status: Expired
Permit Description: RESTROOM ADDITION
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/21/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T18CM02106
Permite Description: RESTROOM ADDITION
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
BUILDING - PROGRESS | N/A | Not Inspected | ||
FIRE SPKLR - FINAL | N/A | Not Inspected | ||
08/31/2018 | BUILDING ABOVE CEILING | N/A | Not ready for Inspection | IVRS - Inspection :* |
10/08/2018 | BUILDING - FINAL | N/A | Partial Approval | Pending air balance report, chlorination report, fire and engineering finals |
Completed Inspections
Permit Status: Expired
Permit Number: T18CM02106
Permit Description: RESTROOM ADDITION
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | |
07/30/2018 | BUILDING PRE-SLAB | RCAMACH1 | Approved | IVRS - Inspection :* |
08/03/2018 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | |
08/10/2018 | REINFORCED MASONRY PRE-GROUT | RCAMACH1 | Approved | IVRS - Inspection :* |
08/14/2018 | ROOF NAILING | mramber1 | Approved | |
08/31/2018 | PLUMBING - INTERMEDIATE | RCAMACH1 | Approved | IVRS - Inspection :* |
08/31/2018 | ELECTRIC - INTERMEDIATE | RCAMACH1 | Approved | IVRS - Inspection :* |
08/31/2018 | FRAMING | RCAMACH1 | Approved | IVRS - Inspection :* |
09/05/2018 | SHEET ROCK NAILING | RCAMACH1 | Approved | IVRS - Inspection :* |
10/03/2018 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
10/03/2018 | ELECTRIC - FINAL | RCAMACHO | Approved | |
10/03/2018 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
10/03/2018 | MECHANICAL - ABOVE CEILING | RCAMACHO | Approved | |
10/08/2018 | ENGINEERING - FINAL | DROBERTS | Approved | |
10/10/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |
11/01/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | APPROVAL SENT TO RECORDS |
11/01/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |