Permit: T18CM00897
Permit Details
Apply Date:
02/05/2018
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI: OFFICE
Architects:
- GOLDSTEIN GENE
Contractors:
- INNOVATIVE TECHNOLOGY DEVELOPMENT GROUP LLC
Permit Reviews
Permit Number - T18CM00897
Permit Status: C of o
Permit Description: TI: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2018 | PLANS OK TO SUBMIT - COMM | 02/06/2018 | COMPLETED |
| 02/07/2018 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 03/13/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM00897
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/05/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T18CM00897
Permit Description: TI: OFFICE
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/04/2018 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED NORTH SIDE OF BUILING |
| 04/04/2018 | FRAMING | ESTEVEN1 | Approved | APPROVED NORTH SIDE OF BUILING |
| 04/06/2018 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED NORTH SIDE |
| 04/12/2018 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 04/12/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 04/12/2018 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
| 05/07/2018 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | NORTH SIDE |
| 05/07/2018 | ELECTRIC - TEMPORARY SERVICE | ESTEVEN1 | Approved | |
| 05/07/2018 | ELECTRIC - SERVICE UPGRADE | ESTEVEN1 | Approved | |
| 05/25/2018 | MECHANICAL - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/25/2018 | BUILDING - PROGRESS | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/25/2018 | PLUMBING - PROGRESS | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/29/2018 | PLUMBING - PRE SLAB | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/29/2018 | ELECTRIC - PROGRESS | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/08/2018 | FIRE - FINAL | gsereno1 | Approved | |
| 06/11/2018 | PLUMBING - ABOVE CEILING | BBENEDO1 | Approved | |
| 06/11/2018 | MECHANICAL - PROGRESS | BBENEDO1 | Approved | |
| 06/11/2018 | MECHANICAL - INTERMEDIATE | BBENEDO1 | Approved | |
| 06/11/2018 | ELECTRIC - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 06/11/2018 | PLUMBING - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 07/03/2018 | BUILDING - FINAL | BBENEDO1 | Approved | FIRE AND ENGINEERING APPROVED |
| 07/03/2018 | FIRE SPKLR - FINAL | GSERENO1 | Approved | AOPROVED PER C.BALSALDA APPROVAL SENT TO RECORDS |
| 07/03/2018 | ENGINEERING - FINAL | DROBERTS | Approved |