Permit: T18CM00845
Permit Details
Status:
Final
Type:
SINGLE FAMILY NEW
Address:
3303 N TYNDALL AV #01
Address NEW:
3303 N TYNDALL AV #01
Apply Date:
02/02/2018
Applicant:
BLUESTONE DESIGN & CONSTRUCTION LLC
Description:
NEW DUPLEX
Contractors:
- BLUESTONE DESIGN & CONSTRUCTION LLC
Permit Reviews
Permit Number - T18CM00845
Permit Status: Final
Permit Description: NEW DUPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/02/2018 | PLANS OK TO SUBMIT - RES | 02/02/2018 | COMPLETED |
| 02/05/2018 | RESIDENTIAL - BLDG/WWM | 07/16/2018 | COMPLETED |
| 02/19/2019 | RESUBMITTAL | 06/10/2019 | COMPLETED |
| 06/17/2019 | REVISION - - 1ST | 06/17/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T18CM00845
Permit Status: Final
Permit Description: NEW DUPLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/02/2018 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T18CM00845
Permit Description: NEW DUPLEX
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/11/2019 | BUILDING PRE-SLAB | RCHANDLER | Approved | Completed on permit T18CM00871. |
| 06/11/2019 | STEM WALL/RETAINING WALL | RCHANDLER | Approved | Completed on permit T18CM00871. |
| 06/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | RCHANDLER | Approved | Completed on permit T18CM00871. |
| 06/11/2019 | ROOF NAILING | RCHANDLER | Approved | |
| 06/11/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 06/20/2019 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | |
| 06/20/2019 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | |
| 06/20/2019 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | |
| 06/20/2019 | U VALUE FOR WINDOW | RCAMACHO | Approved | |
| 06/20/2019 | STUCCO MESH | RCAMACHO | Approved | |
| 06/24/2019 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENCIA | Approved | |
| 06/26/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | |
| 06/26/2019 | FRAMING | TVALENCIA | Approved | |
| 06/26/2019 | PLUMBING - INTERMEDIATE | TVALENCIA | Approved | 1- Shall provide a Mission Specialty coupling on the 11/2 vertical lavatory vent. 2- Shall locate the horizontal vent for the Tubs 6 inches above the flood level rim of the fixture. 3- Re test the system. |
| 06/26/2019 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | |
| 06/26/2019 | TEP CLEARANCE - PM | TVALENCIA | Approved | UNIT #01 & #02 CODE ECO |
| 06/26/2019 | ELECTRIC - CONSTRUCTION POWER | TVALENCIA | Approved | Clear electric eco Unit 1 and Unit 2 |
| 06/26/2019 | FRAMING | TVALENCIA | Approved | |
| 07/25/2019 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | For units 1 and 2 |
| 07/25/2019 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | For units 1 and 2 |
| 08/16/2019 | ZONING - FINAL | DROBERTS | Approved | 5 BEDROOMS NOTED WITHIN THE STRUCTURE |
| 08/16/2019 | ZONING - FINAL | DROBERTS | Approved | APPROVED PER DROBERTS |
| 08/26/2019 | OUTDOOR LIGHTING FINAL | TVALENCIA | Approved | |
| 08/26/2019 | ELECTRIC - UFER | TVALENCIA | Approved | |
| 08/27/2019 | MECHANICAL - FINAL | DQUINN | Approved | |
| 08/27/2019 | PLUMBING - FINAL | DQUINN | Approved | |
| 08/27/2019 | ELECTRIC - FINAL | DQUINN | Approved | |
| 08/27/2019 | BUILDING - FINAL | DQUINN | Approved |