Permit: T17RW04220
Permit Details
Apply Date:
09/25/2017
Applicant:
TUCSON EXPEDITING & DEVELOPMENT
Description:
SIDEWALK CLOSURE FOR TEMPORARY CONSTRUCTION TRAILER PLACEMENT 03/02/2018-LANE CLOSURE FOR CONCRETE POUR 8PM-6AM 03/13/2018-PLAN CHANGE- 24 HOUR 03/22/2018-CHANGE TO INCLUDE OVERNIGHT CONCRETE POUR MARCH 22-23 AND APRIL 2-3, 2018 PER TNE. MARCH 22 AND 23- BEGIN AT 2AM AND END AT 6AM APRIL 2 AND 3 -BEGIN AT 1AM AND ENDING AT 6AM 06/27/2018-PLAN CHANGE-24 HOUR CLOSURE 07/23/18 - PLAN CHANGE TO INCLUDE FULL CLOSURE DURING CLEAN-UP OF ON-SITE FIRE THROUGH 08/3/18 AND OVERNIGHT CONCRETE POURS 7/17/18, 07/27/18 & 07/31/18 PER TNE. 07/252018-PLAN CHANGE- PLAN CHANGE TO INCLUDE CONNECTIONS TO STORM DRAINS IN THE ROW AT SOUTHEAST AND SOUTHWEST CORNERS OF THE PROJECT. 8/1/18 TNE FOR JULY 31 CHANGED TO AUGUST 4
Completed Inspections
Permit Status: Final
Permit Number: T17RW04220
Permit Description: SIDEWALK CLOSURE FOR TEMPORARY CONSTRUCTION TRAILER PLACEMENT
03/02/2018-LANE CLOSURE FOR CONCRETE POUR
8PM-6AM
03/13/2018-PLAN CHANGE- 24 HOUR
03/22/2018-CHANGE TO INCLUDE OVERNIGHT CONCRETE POUR MARCH 22-23 AND APRIL 2-3, 2018 PER TNE.
MARCH 22 AND 23- BEGIN AT 2AM AND END AT 6AM
APRIL 2 AND 3 -BEGIN AT 1AM AND ENDING AT 6AM
06/27/2018-PLAN CHANGE-24 HOUR CLOSURE
07/23/18 - PLAN CHANGE TO INCLUDE FULL CLOSURE DURING CLEAN-UP OF ON-SITE FIRE THROUGH 08/3/18 AND OVERNIGHT CONCRETE POURS 7/17/18, 07/27/18 & 07/31/18 PER TNE.
07/252018-PLAN CHANGE-
PLAN CHANGE TO INCLUDE CONNECTIONS TO STORM DRAINS IN THE ROW AT SOUTHEAST AND SOUTHWEST CORNERS OF THE PROJECT.
8/1/18 TNE FOR JULY 31 CHANGED TO AUGUST 4
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/04/2018 | TDOT-EXCAV GENERAL INSPECTION | MVV | Approved | Barricades in place. |