Permit Details

Status:
Expired
Type:
Commercial Building
Address:
875 W CUSHING ST
Address NEW:
875 W CUSHING ST
Apply Date:
12/06/2017
Applicant:
Description:
E- PARKING STRUCTURE FOR CATERPILLAR SM&T HQ

Permit Reviews

Permit Number - T17CM08994
Permit Status: Expired
Permit Description: E- PARKING STRUCTURE FOR CATERPILLAR SM&T HQ
Start Date Submittal Complete Date Status  
02/04/2019 REVISION - - 1ST 02/21/2019 COMPLETED Review Details
11/27/2018 REVISION - - 1ST 02/04/2019 COMPLETED Review Details
12/06/2017 PLANS OK TO SUBMIT - COMM 12/06/2017 COMPLETED Review Details
12/22/2017 COMMERCIAL - NEW 11/27/2018 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM08994
Permit Status: Expired
Permit Description: E- PARKING STRUCTURE FOR CATERPILLAR SM&T HQ
Total Outstanding Activity Conditions - 1
Date Name
12/06/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Conditions

Permit Number - T17CM08994
Permit Status: Expired
Permit Description: E- PARKING STRUCTURE FOR CATERPILLAR SM&T HQ
Date Description Comments
12/22/2017 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
12/22/2017 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
12/22/2017 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
12/22/2017 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
12/22/2017 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
12/22/2017 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
12/22/2017 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
12/22/2017 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.

Outstanding Inspections

Permit Status: Expired
Permit Number: T17CM08994
Permite Description: E- PARKING STRUCTURE FOR CATERPILLAR SM&T HQ
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/07/2022 TRSP - ROW - Final/Close-Out N/A Canceled Inspection Canceled

Completed Inspections

Permit Status: Expired
Permit Number: T17CM08994
Permit Description: E- PARKING STRUCTURE FOR CATERPILLAR SM&T HQ
Total Completed Inspections - 25
Date Description Inspector Results Comments
12/28/2018 COT - LCPL - Rough Soil Passed {Activity date: 12/28/2018; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - }
03/01/2019 COT - LCBU - Stem Wall/Retaining Wall Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 01/10/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - completion of crash walls per detail 211/S 4.1
completion of column tops for future solar
} ; {Activity date: 01/08/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Crush wall per detail 211/S 4.1 GL M from 2-4 & GL 1 from J-L
Column tops for future solar Gridline 3 from J to M} ; {Activity date: 01/03/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Level 1 garage crash wall per detail 211. GL 6 from G-M & GL M from 4-6.
Level 1 column tops for future solar GL 4 from G-M}
03/01/2019 COT - LCEL - Electrical Intermediate Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 02/13/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - All panels and transformer OK to energize for test only} ; {Activity date: 12/18/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Level 1 garage slab GL 1-6 from H-M}
03/01/2019 COT - LCEL - Electrical Underground Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 12/18/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Level 1 garage slab GL 1-6 from H-M}
03/01/2019 COT - LCPL - Plumbing Roof Drains Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - }
03/01/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CBELL1 - }
03/01/2019 COT - LCPL - Plumbing Intermediate Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 12/28/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - except fitness center}
03/01/2019 COT - LCEL - Electrical Final Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - }
03/01/2019 PDSD Building Division - Sign Final Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CBELL1 - }
03/01/2019 COT - LCBU - Building Progress Passed {Activity date: 03/01/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 11/28/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - 2nd floor column tops for future solar grid line 1 to 6 from a to D only}
04/12/2019 COT - LCBU - Building Above Ceiling Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by AVAUGHN1 - PER 1090} ; {Activity date: 03/01/2019; Status: Not Applicable; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 12/28/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - level 2 Gridline 2-5 from A-C except room 2030}
04/12/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - Note landscaping depressed areas will be re-inspected under the DP permit and requires 6 inches of clear space below curb openings} ; {Activity date: 03/01/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by CBELL1 - Complete all work on approved plans.}
04/12/2019 COT - LCBU - Building Final Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } ; {Activity date: 03/01/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Except stairs and guard rails
Pending fire and engineering finals}
04/12/2019 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } ; {Activity date: 03/01/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Except north stairwell footers} ; {Activity date: 02/25/2019; Status: Not ready for Inspection; Inspector: RCAMACHO; Comment: Entered by CBELL1 - work not complete} ; {Activity date: 02/22/2019; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by CBELL1 - East side of garage bridge expansion joint OK to pour.} ; {Activity date: 02/06/2019; Status: Not ready for Inspection; Inspector: TVALENCIA; Comment: Entered by CBELL1 - Contractor cancelled the inspection request} ; {Activity date: 02/01/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Northbridge ramp only} ; {Activity date: 01/16/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Stairwell to parking lot canopy} ; {Activity date: 01/07/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - garage bridges north and west see RFI 368}
04/12/2019 COT - LCEL - Outdoor Lighting Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } ; {Activity date: 03/01/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Pending any special inspections}
04/12/2019 COT - LCBU - Preslab Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } ; {Activity date: 03/28/2019; Status: Partial Approval; Inspector: BSTEVENS; Comment: Entered by CBELL1 - OK to pour garage stairs} ; {Activity date: 02/25/2019; Status: Not ready for Inspection; Inspector: RCAMACHO; Comment: Entered by CBELL1 - work not complete} ; {Activity date: 02/01/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Northbridge ramp only} ; {Activity date: 01/16/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Stairwell to parking lot canopy} ; {Activity date: 01/07/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - garage bridges north and west see RFI 368} ; {Activity date: 12/18/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Level 1 garage slab GL 1-6 from H-M} ; {Activity date: 12/14/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - See permit T17cm08953
Entire bottom level GL 1-6 from A-M
Level 1 GL 1-6 from A-H
Garage parapet GL1 from B to E
Garage parapet GL 6 from D to F
Level 1 2nd floor column tops for future solar GL
E-G from 1 to 6} ; {Activity date: 11/30/2018; Status: Partial Approval; Inspector: MRAMBER; Comment: Entered by CBELL1 - N.W. corner of 1st pour, parapet wall C.L. C to B and 20 foot south ok}
04/12/2019 ENGR Engineering Final Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - Note landscaping depressed areas will be re-inspected under the DP permit and requires 6 inches of clear space below curb openings} ; {Activity date: 03/01/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by CBELL1 - walked site with GC went over work to complete.}
04/12/2019 COT - LCPL - Plumbing Above Ceiling Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by AVAUGHN1 - PER 3037} ; {Activity date: 03/01/2019; Status: Not Applicable; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 12/28/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - level 2 Gridline 2-5 from A-C except room 2030}
04/12/2019 COT - FCON - Fire - Final Passed {Activity date: 04/12/2019; Status: Approved; Inspector: jvincent; Comment: Entered by JVINCEN1 - will add extinguisher signs to posts/wall. extinguishers will be obstructed by parked vehicles.} ; {Activity date: 03/01/2019; Status: Partial Approval; Inspector: jvincent; Comment: Entered by MROSS2 - Approved to obtain TCO. Ok to occupy/park on lower level. Install extinguisher cabinets and extinguishers. Garage not sprinklered or alarmed.}
04/12/2019 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 04/12/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by AVAUGHN1 - PER 2090} ; {Activity date: 03/01/2019; Status: Not Applicable; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 12/28/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - level 2 Gridline 2-5 from A-C except room 2030}
04/12/2019 COT - LCPL - Plumbing Final Passed {Activity date: 04/12/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - } ; {Activity date: 03/01/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Insulate exposed copper at hose bib}
04/16/2019 COT - LCBU - Framing Passed {Activity date: 04/16/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by AVAUGHN1 - PER 1090} ; {Activity date: 03/01/2019; Status: Not Applicable; Inspector: RCAMACHO; Comment: Entered by CBELL1 - }
04/16/2019 COT - LCME - Mechanical Above Ceiling Passed {Activity date: 04/16/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by AVAUGHN1 - } ; {Activity date: 03/01/2019; Status: Not Applicable; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 12/28/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - level 2 Gridline 2-5 from A-C except room 2030}
04/16/2019 COT - LCBU - Exterior Clips/Sheathing Passed {Activity date: 04/16/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by AVAUGHN1 - PER 1090} ; {Activity date: 04/12/2019; Status: Not Applicable; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - }
04/16/2019 COT - LCBU - Roof Nailing Passed {Activity date: 04/16/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by AVAUGHN1 - PER 1090} ; {Activity date: 03/01/2019; Status: Not Applicable; Inspector: RCAMACHO; Comment: Entered by CBELL1 - }