Permit: T17CM08410
Permit Details
Apply Date:
11/09/2017
Applicant:
RAFAEL GHINS
Description:
2 BED/ 2 BATH ADDITION
Permit Reviews
Permit Number - T17CM08410
Permit Status: Final
Permit Description: 2 BED/ 2 BATH ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/09/2017 | PLANS OK TO SUBMIT - RES | 11/09/2017 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T17CM08410
Permit Description: 2 BED/ 2 BATH ADDITION
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/12/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED |
| 12/20/2017 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | MISSING FOOTING AGAINST THE REAR WALL OF EXSISTING BUILDING |
| 12/21/2017 | BUILDING PRE-SLAB | rbaldwin | Approved | |
| 12/27/2017 | ELECTRIC - SERVICE UPGRADE | ESTEVEN1 | Approved | APPROVED INCR |
| 12/28/2017 | TEP CLEARANCE - AM | ESTEVENS | Approved | INCR |
| 01/12/2018 | ROOF NAILING | ESTEVEN1 | Approved | APPROVED |
| 01/17/2018 | U VALUE FOR WINDOW | NORTH | Approved | |
| 01/19/2018 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 01/19/2018 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 01/19/2018 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
| 01/19/2018 | FRAMING | ESTEVEN1 | Approved | APPROVED |
| 02/01/2018 | STUCCO MESH | NORTH | Approved | |
| 06/29/2018 | PLUMBING - GAS PRESSURE TEST | DFLORES2 | Approved | |
| 06/29/2018 | ELECTRIC - FINAL | DFLORES2 | Approved | |
| 06/29/2018 | MECHANICAL - FINAL | DFLORES2 | Approved | IVRS - Inspection :* |
| 06/29/2018 | PLUMBING - FINAL | DFLORES2 | Approved | IVRS - Inspection :* |
| 06/29/2018 | BUILDING - FINAL | DFLORES2 | Approved | IVRS - Inspection :* |