Permit: T17CM08117
Permit Details
Apply Date:
10/30/2017
Applicant:
LECHNER CONSTRUCTION INC ,
Description:
RETAIL STORE
Contractors:
- LECHNER CONSTRUCTION INC ,
Permit Reviews
Permit Number - T17CM08117
Permit Status: C of o
Permit Description: RETAIL STORE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/17/2018 | RESUBMITTAL | 02/16/2018 | COMPLETED |
| 05/07/2018 | REVISION - - 1ST | 05/07/2018 | COMPLETED |
| 10/30/2017 | PLANS OK TO SUBMIT - COMM | 10/31/2017 | COMPLETED |
| 10/31/2017 | COMMERCIAL - NEW | 11/27/2017 | COMPLETED |
| 12/18/2017 | RESUBMITTAL | 01/11/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM08117
Permit Status: C of o
Permit Description: RETAIL STORE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/30/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM08117
Permit Description: RETAIL STORE
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2018 | PLUMBING - ROUGH, SOIL | NORTH | Approved | |
| 02/28/2018 | ELECTRIC - TEMPORARY SERVICE | NORTH | Approved | |
| 03/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | BJones | Approved | |
| 03/14/2018 | BUILDING PRE-SLAB | BJones | Approved | |
| 03/23/2018 | STEM WALL/RETAINING WALL | DFLORES2 | Approved | |
| 04/02/2018 | ELECTRIC - UNDERGROUND | BJones | Approved | |
| 04/09/2018 | EXT METAL CLIPS/EXT SHEATHING | BJones | Approved | |
| 04/09/2018 | PLUMBING - SEWER HCS CONNECT | BJones | Approved | |
| 04/12/2018 | ELECTRIC - INTERMEDIATE | BJONES | Approved | Electric Panel not set at this time |
| 04/13/2018 | PLUMBING - INTERMEDIATE | BJones | Approved | |
| 04/13/2018 | PLUMBING - INTERMEDIATE | BJONES | Approved | Needs Test on Waste and Vent |
| 04/20/2018 | SHEET ROCK NAILING | BJones | Approved | |
| 05/08/2018 | ELECTRIC - CONSTRUCTION POWER | BJones | Approved | |
| 05/08/2018 | ELECTRIC - ABOVE CEILING | BJones | Approved | |
| 05/09/2018 | TEP CLEARANCE - AM | BJONES | Approved | ECO |
| 06/11/2018 | ELECTRIC - FINAL | mramber1 | Approved | |
| 06/11/2018 | PLUMBING - PROGRESS | mramber1 | Approved | |
| 06/11/2018 | FRAMING | mramber1 | Approved | |
| 06/12/2018 | MECHANICAL - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE REPORT COMPLETED |
| 06/13/2018 | PLUMBING - FINAL | BJONES | Approved | |
| 06/13/2018 | PLUMBING - YARD WTR LINE/TEST | BJONES | Approved | |
| 06/13/2018 | BUILDING - FINAL | BJONES | Approved | APPROVALS BY R SHERRY-M&P AND D ROBERTS ENG |
| 06/13/2018 | BUILDING - PROGRESS | BJONES | Approved | |
| 06/13/2018 | U VALUE FOR WINDOW | BJONES | Approved | |
| 06/13/2018 | BUILDING ABOVE CEILING | BJONES | Approved | |
| 06/13/2018 | ROOF NAILING | BJONES | Approved | |
| 06/13/2018 | MECHANICAL - INTERMEDIATE | BJONES | Approved | |
| 06/13/2018 | MECHANICAL - ABOVE CEILING | BJONES | Approved | |
| 06/13/2018 | OUTDOOR LIGHTING FINAL | BJONES | Approved | NO REQUIREMENT FOR SPECIAL INSPECTION BY 3RD PARTY. ALL LIGHTING CALCULATIONS INCLUDED IN SUBMITAL FOR PERMIT ISSUANCE. |
| 06/13/2018 | ELECTRIC - OUTDOOR LIGHTING | BJONES | Approved | |
| 06/13/2018 | ELECTRIC - UFER | BJONES | Approved | |
| 06/13/2018 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 06/14/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
| 06/14/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
| 06/14/2018 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
| 06/15/2018 | CERTIFICATE OF OCCUPANCY | BJONES | Approved | |
| 06/15/2018 | ELECTRIC - PROGRESS | BJONES | Approved |