Permit: T17CM07988
Permit Details
Apply Date:
10/24/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
CONVERT SHELL TO WARM SHELL
Architects:
- MARLEY, EDWARD TODD
Contractors:
- PATE CONTRACTORS LLC
Permit Reviews
Permit Number - T17CM07988
Permit Status: L of c
Permit Description: CONVERT SHELL TO WARM SHELL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/24/2017 | COMMERCIAL - TI | 11/03/2017 | COMPLETED |
11/03/2017 | RESUBMITTAL | 12/08/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07988
Permit Status: L of c
Permit Description: CONVERT SHELL TO WARM SHELL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/24/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM07988
Permit Description: CONVERT SHELL TO WARM SHELL
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/03/2018 | FRAMING | mramber1 | Approved | |
01/03/2018 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
01/16/2018 | SHEET ROCK NAILING | mramber1 | Approved | |
01/30/2018 | TEP CLEARANCE - AM | MRAMBER | Approved | ECO |
02/01/2018 | MECHANICAL - HYDRONIC PIPING | mramber1 | Approved | |
02/09/2018 | BUILDING ABOVE CEILING | mramber1 | Approved | |
02/09/2018 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | |
02/09/2018 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
03/02/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | |
03/02/2018 | FIRE - FINAL | jvincent | Approved | |
03/02/2018 | FIRE - ALARM FINAL | jvincent | Approved | |
03/02/2018 | FIRE SPKLR - FINAL | jvincent | Approved | |
03/05/2018 | ELECTRIC - FINAL | MRAMBER | Approved | |
03/05/2018 | MECHANICAL - FINAL | MRAMBER | Approved | |
03/05/2018 | BUILDING - PROGRESS | MRAMBER | Approved | |