Permit: T17CM07725
Permit Details
Apply Date:
10/12/2017
Applicant:
ALEX ENOCH
Description:
SCHOOL
Contractors:
- G 3 REMODELING AND CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM07725
Permit Status: C of o
Permit Description: SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/12/2017 | COMMERCIAL - TI | 10/12/2017 | COMPLETED |
| 10/12/2017 | RESUBMITTAL | 11/13/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07725
Permit Status: C of o
Permit Description: SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/12/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM07725
Permit Description: SCHOOL
Total Completed Inspections - 17
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/12/2017 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 11/28/2017 | ELECTRIC - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 11/28/2017 | FRAMING | TVALENC1 | Approved | IVRS - Inspection :* |
| 11/30/2017 | PLUMBING - INTERMEDIATE | RGREENE1 | Approved | PLUMBING ROUGH SOIL IS OK |
| 12/07/2017 | BUILDING ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* 1- SHALL PROVIDE A REVISED AND APPROVED DRAWING SHOWING THE ADDED GFCI RECEPTICAL OUTLET LOCATED ABOVE THE POOL. |
| 12/07/2017 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 12/07/2017 | BUILDING PRE-SLAB | TVALENC1 | Approved | IVRS - Inspection :* |
| 12/12/2017 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 01/09/2018 | MECHANICAL - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 01/09/2018 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
| 01/11/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
| 01/11/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | NO WORK OUT SIDE BUILDING PER AP PLANS. |
| 01/12/2018 | BUILDING - FINAL | RSHERRY | Approved | Review of air balance report complete |
| 01/12/2018 | BUILDING - FINAL | TVALENCIA | Approved | PENDING AIR BALANCE |
| 01/12/2018 | PLUMBING - FINAL | TVALENCIA | Approved | |
| 01/12/2018 | MECHANICAL - INTERMEDIATE | TVALENCIA | Approved | |
| 01/12/2018 | BUILDING - PROGRESS | TVALENCIA | Approved |