Permit: T17CM07585
Permit Details
Apply Date:
10/06/2017
Applicant:
CARHUFF, PHILIP ANDREW
Description:
NEW APARTMENT BUILDING 12 UNITS
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T17CM07585
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING 12 UNITS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/23/2018 | REVISION - - 1ST | 05/24/2018 | COMPLETED |
| 07/06/2018 | REVISION - - 2ND | 07/06/2018 | COMPLETED |
| 07/24/2018 | REVISION - - 3RD | 07/24/2018 | COMPLETED |
| 10/06/2017 | PLANS OK TO SUBMIT - COMM | 10/06/2017 | COMPLETED |
| 10/12/2017 | COMMERCIAL - NEW | 11/15/2017 | COMPLETED |
| 11/15/2017 | RESUBMITTAL | 12/13/2017 | COMPLETED |
| 12/13/2017 | RESUBMITTAL | 05/04/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07585
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING 12 UNITS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/06/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM07585
Permit Description: NEW APARTMENT BUILDING 12 UNITS
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2017 | FIRE SPKLR - FINAL | RHERNANDEZ | Approved | P2I MAY BE DELETED WHEN THE ROOF AND FLOOR TRUSS DESIGN CALCULATIONS AND DRAWINGS HAVE BEEN REVIEWED AND APPROVED. |
| 12/11/2017 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
| 12/13/2017 | PLUMBING - FINAL | RSHERRY | Approved | WATER CHLORINATION REPORT REQUIRED |
| 07/25/2018 | ELECTRIC - TEMPORARY SERVICE | ESTEVEN1 | Approved | APPROVED TMPP |
| 07/26/2018 | TEP CLEARANCE - AM | ESTEVENS | Approved | TMPP |
| 08/02/2018 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | SUBMIT 2ND PARTIAL ISOMETEIC PLAN, OK TO BACK FILL |
| 08/09/2018 | ELECTRIC - UNDERGROUND | MHASSAN1 | Approved | APPROVED WITHIN FOOTPRINT OF THE RESIDENTIAL BUILDING. |
| 08/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | MHASSAN1 | Approved | FINISH CLEANING OUT FOOTINGS FROM OVERNIGHT RAIN AND INSTALL BLOCKOUTS |
| 08/15/2018 | STEM WALL/RETAINING WALL | ESTEVEN1 | Approved | INTERIOR STEM WALLS |
| 08/23/2018 | BUILDING PRE-SLAB | JBURGE1 | Approved | IVRS - Inspection :* |
| 09/20/2018 | BUILDING - PROGRESS | DFLORES | Approved | THIS INSPECTION WAS FOR COULMN BASES ALL ALONG THE SOUTH SIDE OF JOB SITE, NEED TO MAKE SURE RE BAR IS 3" AWAY FROM SOIL ON ALL SIDES |
| 10/04/2018 | PLUMBING - SEWER HCS CONNECT | MHASSAN | Approved | |
| 10/25/2018 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | 2 inch line to one and a half line to all units |
| 11/28/2018 | PLUMBING - PROGRESS | ESTEVENS | Approved | Not under test |
| 11/28/2018 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | Above hard lid area. |
| 12/12/2018 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | units #2105-2108. |
| 12/12/2018 | PLUMBING - INTERMEDIATE | JBURGE | Approved | units #2105-2108. |
| 12/12/2018 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | units 2105-2108 |
| 12/12/2018 | BUILDING ABOVE CEILING | JBURGE | Approved | units #2105-2108. |
| 12/12/2018 | FRAMING | JBURGE | Approved | Building #2; units #2105-2108. Ok to insulate and sheetrock. |
| 12/19/2018 | SHEET ROCK NAILING | TVALENCIA | Approved | |
| 12/19/2018 | U VALUE FOR WINDOW | TVALENCIA | Approved | |
| 12/19/2018 | STUCCO MESH | TVALENCIA | Approved | |
| 12/19/2018 | ROOF NAILING | TVALENCIA | Approved | |
| 12/19/2018 | EXT METAL CLIPS/EXT SHEATHING | TVALENCIA | Approved | |
| 01/29/2019 | ELECTRIC - SERVICE UPGRADE | JBURGE | Approved | Called in for clearance at 1420 hours |
| 01/29/2019 | ELECTRIC - UFER | JBURGE | Approved | |
| 04/19/2019 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 04/19/2019 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | |
| 04/19/2019 | ELECTRIC - PROGRESS | JBURGE | Approved | |
| 04/29/2019 | ELECTRIC - CONSTRUCTION POWER | ESTEVENS | Approved | |
| 04/29/2019 | ELECTRIC - TEMPORARY POLE | ESTEVENS | Approved | |
| 04/29/2019 | MECHANICAL - PROGRESS | ESTEVENS | Approved | |
| 04/30/2019 | ELECTRIC - FINAL | TVALENCIA | Approved | |
| 10/14/2019 | ENGINEERING - FINAL | BBENEDON | Approved | |
| 10/15/2019 | CERTIFICATE OF OCCUPANCY | DROBERTS | Approved | |
| 10/15/2019 | BUILDING - FINAL | DROBERTS | Approved | |
| 10/15/2019 | ZONING - FINAL | ACONNOR | Approved | RECORDED EASEMENT SEQ # 20191510634 |
| 10/15/2019 | ZONING - FINAL | DROBERTS | Approved | FINAL CAN BE GIVEN UNDER MY NAME ONCE THE EASMENT IN QUESTION HAS BEEN DETERTMINED AND APPROVED BY THE ZONING REVIEWER. |
| 10/15/2019 | BUILDING - FINAL | DROBERTS | Approved | FINAL CAN BE GIVEN UNDER MY NAME ONCE THE EASMENT IN QUESTION HAS BEEN DETERTMINED AND APPROVED BY THE ZONING REVIEWER. |
| 10/15/2019 | CERTIFICATE OF OCCUPANCY | DROBERTS | Approved | FINAL CAN BE GIVEN UNDER MY NAME ONCE THE EASMENT IN QUESTION HAS BEEN DETERTMINED AND APPROVED BY THE ZONING REVIEWER. |
| 10/15/2019 | FIRE - FINAL | JPEELDAVIS | Approved | approved by Chris Basaldua on 04-29-2019 |
| 10/15/2019 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | Fire sprinkler was approved by Chris Basaldua on permit T18FC00992 on 04-29-2019 |