Permit: T17CM07415
Permit Details
Apply Date:
09/28/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Architects:
- JUNO, KEVIN R
Contractors:
- CONCEPT COMMERCIAL CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM07415
Permit Status: C of o
Permit Description: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/28/2017 | COMMERCIAL - TI | 10/23/2017 | COMPLETED |
10/23/2017 | RESUBMITTAL | 10/25/2017 | COMPLETED |
10/25/2017 | RESUBMITTAL | 10/31/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM07415
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/28/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM07415
Permit Description: RETAIL
Total Completed Inspections - 21
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/25/2017 | MECHANICAL - FINAL | RSHERRY | Approved | AIR BALANCE REPORT REQUIRED |
10/25/2017 | PLUMBING - FINAL | RSHERRY | Approved | WATER CHLORINATION REPORT REQUIRED |
11/21/2017 | PLUMBING - ROUGH, SOIL | BBENEDO1 | Approved | IVRS - Inspection :* |
12/13/2017 | MECHANICAL - INTERMEDIATE | RGREENE1 | Approved | |
12/13/2017 | PLUMBING - INTERMEDIATE | RGREENE1 | Approved | |
12/13/2017 | ELECTRIC - INTERMEDIATE | RGREENE1 | Approved | |
12/13/2017 | FRAMING | RGREENE1 | Approved | |
01/03/2018 | PLUMBING - ABOVE CEILING | RGREENE1 | Approved | |
01/03/2018 | ELECTRIC - ABOVE CEILING | RGREENE1 | Approved | |
01/19/2018 | TEP CLEARANCE - AM | RGREENE | Approved | INCR |
01/19/2018 | ENGINEERING - FINAL | MRUSSO | Approved | |
01/30/2018 | BUILDING ABOVE CEILING | RGREENE1 | Approved | |
02/06/2018 | FIRE SPKLR - FINAL | gsereno1 | Approved | Approved by CB on 2/1/18. |
02/06/2018 | ELECTRIC - FINAL | DQUINN | Approved | |
02/08/2018 | PLUMBING - PROGRESS | DQUINN | Approved | |
02/08/2018 | SHEET ROCK NAILING | DQUINN | Approved | |
02/09/2018 | FIRE - FINAL | gsereno1 | Approved | |
02/09/2018 | FIRE - ALARM FINAL | gsereno1 | Approved | |
02/13/2018 | HEALTH DEPT - FINAL 724-7908 | PURBINA | Approved | |
02/13/2018 | CERTIFICATE OF OCCUPANCY | PURBINA | Approved | |
02/15/2018 | BUILDING - FINAL | RSHERRY | Approved | REVIEW OF AIR BALANCE AND WATER CHLORINATION TEST REPORTS COMPLETE |