Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/15/2018 | BUILDING - FINAL | Approved | REVIEW OF AIR BALANCE AND WATER CHLORINATION TEST REPORTS COMPLETE | |
| 02/14/2018 | BUILDING - FINAL | Partial Approval | PEDNING AIR AND WATER TEST | |
| 02/09/2018 | BUILDING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999 1- SHALL PROVIDE A THERMOMETER ON THE HOT WATER LINE SUPPLY FROM THE WATER HEATER. 2- SHALL PROVIDE A VACUUM RELIEF VALVE ON THE COLD WATER SUPPLY TO T5HE WATER HEATER. 3- SHALL SUPPORT THE EXPANSION TANK. 4- SHALL DISCHARGE THE WATER HEATER T & P DRAIN TO THE MOP SINK AS PER PLAN. 5- SHALL PROVIDE A WATTS 1022 IN LINE BACKFLOW PREVENTER FOR BOTH ICE MACHINES. * |