Permit: T17CM06861
Permit Details
Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
2644 E SPEEDWAY BL
Address NEW:
2644 E SPEEDWAY BL
Apply Date:
09/07/2017
Applicant:
REX, CATHERINE APPLEGATE
Description:
T16DV04817 CAR INTO BUILDING
Architects:
- REX, CATHERINE APPLEGATE
Contractors:
- AMERICAN TECHNOLOGIES INC
Permit Reviews
Permit Number - T17CM06861
Permit Status: L of c
Permit Description: T16DV04817 CAR INTO BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/07/2017 | COMMERCIAL - TI | 10/12/2017 | COMPLETED |
| 11/17/2017 | REVISION - - 1ST | 11/17/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM06861
Permit Status: L of c
Permit Description: T16DV04817 CAR INTO BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/07/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM06861
Permit Description: T16DV04817 CAR INTO BUILDING
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/10/2017 | PLUMBING - FINAL | RSHERRY | Approved | WATER CHLORINATION REPORT REQUIRED. |
| 10/27/2017 | FIRE - FINAL | jvincent | Approved | |
| 11/17/2017 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | OK TO TOP-OUT AND ROUT COLUMN AT 8' - 12' |
| 12/04/2017 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | EXTERIOR SIGNAGE: ELECTRIC WIRING NEEDS TO BE PULLED. |
| 12/04/2017 | BUILDING - PROGRESS | JBURGE | Approved | |
| 12/04/2017 | FRAMING | JBURGE | Approved | |
| 12/04/2017 | FRAMING | JBURGE | Approved | |
| 12/04/2017 | ROOF NAILING | JBURGE | Approved | |
| 12/13/2017 | STUCCO MESH | ESTEVEN1 | Approved | APPROVED |
| 02/05/2018 | U VALUE FOR WINDOW | ESTEVEN1 | Approved | APROVED SAFETY GLASS |
| 03/06/2018 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | OK TO COVER CEILINGS. |
| 03/13/2018 | SHEET ROCK NAILING | JBURGE | Approved | OK TO TAPE THROUGHOUT. |
| 05/09/2018 | ELECTRIC - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/09/2018 | BUILDING - FINAL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 05/10/2018 | PLUMBING - INTERMEDIATE | bbenedo1 | Approved | |
| 05/10/2018 | BUILDING ABOVE CEILING | bbenedo1 | Approved | |
| 05/10/2018 | EXT METAL CLIPS/EXT SHEATHING | bbenedo1 | Approved | |
| 05/10/2018 | ENGINEERING - FINAL | MRUSSO | Approved |