Permit Details

Status:
L of c
Type:
COMMERCIAL ALTERATION
Apply Date:
08/11/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
TI:GI LAB EQUIPMENT UPGRADE
Architects:
  • BOLLARD, MARK EDWARD
Contractors:
  • B F L CONSTRUCTION CO INC ,

Permit Reviews

Permit Number - T17CM06209
Permit Status: L of c
Permit Description: TI:GI LAB EQUIPMENT UPGRADE
Start Date Submittal Complete Date Status  
08/11/2017 COMMERCIAL - TI 08/18/2017 COMPLETED Review Details
08/18/2017 COMMERCIAL - TI 10/03/2017 COMPLETED Review Details
10/03/2017 RESUBMITTAL 10/23/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM06209
Permit Status: L of c
Permit Description: TI:GI LAB EQUIPMENT UPGRADE
Total Outstanding Activity Conditions - 1
Date Name
08/11/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: L of c
Permit Number: T17CM06209
Permit Description: TI:GI LAB EQUIPMENT UPGRADE
Total Completed Inspections - 23
Date Description Inspector Results Comments
12/07/2017 PLUMBING - MD GAS/PRECONST MTG JBURGE Approved
12/19/2017 PLUMBING - MEDICAL GAS/TEST JBURGE Approved CARBON DIOXIDE LINE AT 1/2" - UP TO JUNCTION OF EXPANXION JOIN. PHASE I IS COMPLETE.
04/19/2018 MECHANICAL - ABOVE CEILING JBURGE Approved OK TO INSULATE DUCT SYSTEM.
05/07/2018 PLUMBING - ABOVE CEILING JBURGE Approved
05/07/2018 PLUMBING - INTERMEDIATE JBURGE Approved
06/01/2018 ELECTRIC - ABOVE CEILING JBURGE Approved
06/06/2018 FRAMING JBURGE Approved OK TO COVER WALLS
06/06/2018 ELECTRIC - INTERMEDIATE JBURGE Approved OK TO COVER WALLS.
07/13/2018 ELECTRIC - FINAL JBURGE Approved
07/13/2018 BUILDING - PROGRESS JBURGE Approved
07/13/2018 SHEET ROCK NAILING JBURGE Approved
07/13/2018 FIREWALL/FIREBARRIER/FIRESTOP JBURGE Approved
07/13/2018 BUILDING ABOVE CEILING JBURGE Approved
07/13/2018 MECHANICAL - INTERMEDIATE JBURGE Approved
07/13/2018 MECHANICAL - HYDRONIC PIPING JBURGE Approved
07/13/2018 ENGINEERING - FINAL JBURGE Approved
07/27/2018 BUILDING - FINAL JBURGE Approved
07/27/2018 PLUMBING - FINAL JBURGE Approved
07/27/2018 PLUMBING - MEDICAL GAS/FINAL JBURGE Approved
07/27/2018 MECHANICAL - FINAL JBURGE Approved
07/27/2018 FIRE - FINAL jvincent Approved
07/27/2018 FIRE - ALARM FINAL jvincent Approved
07/27/2018 FIRE SPKLR - FINAL jvincent Approved

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW