Permit: T17CM05919
Permit Details
Apply Date:
08/02/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
SFR MESQ192715 T15-M0028
Contractors:
- OT BUILDERS/MESQUITE HOMES
Permit Reviews
Permit Number - T17CM05919
Permit Status: Final
Permit Description: SFR MESQ192715 T15-M0028
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
08/02/2017 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 08/02/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM05919
Permit Status: Final
Permit Description: SFR MESQ192715 T15-M0028
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
08/02/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM05919
Permit Description: SFR MESQ192715 T15-M0028
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/23/2017 | PLUMBING - SEWER HCS CONNECT | TVALENC1 | Approved | |
08/23/2017 | PLUMBING - YARD WTR LINE/TEST | TVALENC1 | Approved | |
08/23/2017 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | |
09/11/2017 | ELECTRIC - UFER | TVALENC1 | Approved | |
09/11/2017 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | |
09/11/2017 | BUILDING PRE-SLAB | TVALENC1 | Approved | |
09/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | TVALENC1 | Approved | |
09/22/2017 | ROOF NAILING | TVALENC1 | Approved | |
09/22/2017 | EXT METAL CLIPS/EXT SHEATHING | TVALENC1 | Approved | |
09/27/2017 | ELECTRIC - CONSTRUCTION POWER | JMILITE1 | Approved | IVRS - Inspection :* |
09/28/2017 | TEP CLEARANCE - AM | JMILITELLO | Approved | ECO |
09/28/2017 | ELECTRIC - CABLE DROP | JMILITE1 | Approved | OK RES. ECO |
10/09/2017 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | |
10/09/2017 | PLUMBING - GAS PRESSURE TEST | TVALENC1 | Approved | |
10/09/2017 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | |
10/09/2017 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | |
10/09/2017 | U VALUE FOR WINDOW | TVALENC1 | Approved | |
10/10/2017 | STUCCO MESH | TVALENC1 | Approved | IVRS - Inspection :* |
10/10/2017 | FRAMING | TVALENC1 | Approved | IVRS - Inspection :* |
11/06/2017 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
01/17/2018 | OUTDOOR LIGHTING FINAL | NORTH | Approved | |
01/17/2018 | PLUMBING - FINAL | NORTH | Approved | |
01/17/2018 | MECHANICAL - FINAL | NORTH | Approved | |
01/18/2018 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
01/18/2018 | BUILDING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
01/18/2018 | GAS CLEARANCE | BNORTH | Approved |