Permit: T17CM04923
Permit Details
Apply Date:
06/23/2017
Applicant:
N/A
Description:
DEMO; REMODEL AND ADDITION
Architects:
- DOMINGUEZ, PORFIRIO
Contractors:
- CONTRAWEST LLC
Permit Reviews
Permit Number - T17CM04923
Permit Status: Final
Permit Description: DEMO; REMODEL AND ADDITION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/17/2018 | RESUBMITTAL | 05/22/2018 | ACTIVE |
| 05/17/2018 | RESUBMITTAL | 05/17/2018 | COMPLETED |
| 06/23/2017 | PLANS OK TO SUBMIT - RES | 06/23/2017 | COMPLETED |
| 06/23/2017 | RESIDENTIAL - BLDG/WWM | 07/31/2017 | COMPLETED |
| 08/10/2017 | RESUBMITTAL | 05/17/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM04923
Permit Status: Final
Permit Description: DEMO; REMODEL AND ADDITION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/23/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM04923
Permit Description: DEMO; REMODEL AND ADDITION
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | APPROVED |
| 06/15/2018 | ELECTRIC - UFER | GWest | Approved | Rebar an GEC connected/clamped in new footing pour. GEC exits right of Service Panel at the ground in new footing pour at addition. GWest 6-15-2018 |
| 06/19/2018 | STEM WALL/RETAINING WALL | ESTEVEN1 | Approved | APPROVED |
| 06/25/2018 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* |
| 06/27/2018 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | IVRS - Inspection :* |
| 07/02/2018 | BUILDING PRE-SLAB | JBURGE | Approved | OK TO PLACE CONCRETE |
| 08/24/2018 | EXT METAL CLIPS/EXT SHEATHING | MHASSAN1 | Approved | IVRS - Inspection :* |
| 08/24/2018 | ROOF NAILING | MHASSAN1 | Approved | IVRS - Inspection :* |
| 09/19/2018 | PLUMBING - GAS PRESSURE TEST | DFLORES2 | Approved | IVRS - Inspection :* |
| 09/20/2018 | MECHANICAL - INTERMEDIATE | DFLORES | Approved | |
| 09/20/2018 | PLUMBING - INTERMEDIATE | DFLORES | Approved | |
| 09/20/2018 | ELECTRIC - INTERMEDIATE | DFLORES | Approved | |
| 09/20/2018 | FRAMING | DFLORES | Approved | |
| 09/28/2018 | GREEN BUILDING - GENERAL | ESTEVENS | Approved | |
| 10/17/2018 | ELECTRIC - CABLE DROP | DQUINN | Approved | |
| 11/06/2018 | ELECTRIC - CONSTRUCTION POWER | mhassan1 | Approved | ok to clear electric, tmpp |
| 11/07/2018 | TEP CLEARANCE - AM | MHASSAN | Approved | TMPP |
| 01/15/2019 | GAS CLEARANCE | AQUIROZ | Approved | 3050 was approved by DFLORES in Sept, but no clearance sent. Double-checked, Armando ok'ed gas clearance via phone |
| 01/30/2019 | BUILDING - FINAL | JBURGE | Approved | |
| 01/30/2019 | MECHANICAL - FINAL | JBURGE | Approved | |
| 01/30/2019 | PLUMBING - FINAL | JBURGE | Approved | |
| 01/30/2019 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 01/30/2019 | ELECTRIC - FINAL | JBURGE | Approved | |
| 01/30/2019 | STUCCO MESH | JBURGE | Approved | |
| 01/30/2019 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved |