Permit: T17CM04762
Permit Details
Apply Date:
06/20/2017
Applicant:
TOFEL CONSTRUCTION LLC
Description:
TEMP CONSTRUCTION TRAILER
Contractors:
- TOFEL CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM04762
Permit Status: Final
Permit Description: TEMP CONSTRUCTION TRAILER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/20/2017 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/29/2017 | COMPLETED |
| 06/29/2017 | RESUBMITTAL | 06/29/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM04762
Permit Status: Final
Permit Description: TEMP CONSTRUCTION TRAILER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/20/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T17CM04762
Permit Description: TEMP CONSTRUCTION TRAILER
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/09/2017 | TEP CLEARANCE - AM | MRAMBER | Approved | TMPP |
| 08/09/2017 | ENGINEERING - FINAL | mramber1 | Approved | |
| 08/09/2017 | RIGHT OF WAY - FINAL | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - FINAL | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - UFER | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - UNDERGROUND | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - CONSTRUCTION POWER | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - TEMPORARY POLE | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - TEMPORARY SERVICE | mramber1 | Approved | |
| 08/09/2017 | BUILDING - TEMP POWER FOR TEST | mramber1 | Approved | |
| 08/09/2017 | ELECTRIC - SERVICE UPGRADE | mramber1 | Approved | |
| 11/15/2018 | FIRE - FINAL | JPEELDAVIS | Approved |