Permit: T17CM04232
Permit Details
Apply Date:
05/30/2017
Applicant:
WILLARD WETTERLAND
Description:
TI; MEDICAL OFFICE
Contractors:
- B F L CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T17CM04232
Permit Status: L of c
Permit Description: TI; MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/09/2018 | REVISION - - 1ST | 04/12/2018 | COMPLETED |
05/02/2018 | REVISION - - 2ND | 05/02/2018 | COMPLETED |
05/30/2017 | COMMERCIAL - TI | 05/30/2017 | COMPLETED |
05/30/2017 | COMMERCIAL - TI | 06/12/2017 | COMPLETED |
06/21/2017 | RESUBMITTAL | 06/27/2017 | COMPLETED |
06/27/2017 | RESUBMITTAL | 07/20/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM04232
Permit Status: L of c
Permit Description: TI; MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/30/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM04232
Permit Description: TI; MEDICAL OFFICE
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/11/2017 | PLUMBING - ROUGH, SOIL | mramber1 | Approved | |
08/22/2017 | PLUMBING - PRE SLAB | mramber1 | Approved | |
09/08/2017 | PLUMBING - YARD WTR LINE/TEST | DQUINN | Approved | NORTH SIDE WATER MAIN OK TO BURY. |
09/15/2017 | ELECTRIC - CONSTRUCTION POWER | NORTH | Approved | |
10/02/2017 | FRAMING | mramber1 | Approved | |
10/16/2017 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | ok except area east of smoke wall |
10/16/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | ok except area east of smoke wall |
10/16/2017 | PLUMBING - ABOVE CEILING | mramber1 | Approved | ok except area east of smoke wall |
10/30/2017 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | MECH ABOVE IN ADMIN AREA OK |
11/07/2017 | ELECTRIC - PROGRESS | mramber1 | Approved | met with contractor |
11/07/2017 | SHEET ROCK NAILING | mramber1 | Approved | work continuing |
11/17/2017 | ELECTRIC - UFER | mramber1 | Approved | |
11/30/2017 | BUILDING - PROGRESS | mramber1 | Approved | no work |
12/08/2017 | TEP CLEARANCE - AM | MRAMBER | Approved | INCR |
12/08/2017 | ELECTRIC - SERVICE UPGRADE | mramber1 | Approved | |
12/15/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | h-1,h-2,p-1,p-2 and trans ok to energize panels to remain locked |
12/21/2017 | ENGINEERING - FINAL | RLEDONNE | Approved | BOND BEAMS IN SCREEN WALL OK. |
04/03/2018 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
04/10/2018 | FIRE - FINAL | JPEELDAVIS | Approved | |
04/10/2018 | FIRE - ALARM FINAL | JPEELDAVIS | Approved | |
04/10/2018 | BUILDING ABOVE CEILING | mramber1 | Approved | |
04/10/2018 | U VALUE FOR WINDOW | mramber1 | Approved | |
04/10/2018 | PLUMBING - PROGRESS | mramber1 | Approved | |
04/10/2018 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
04/10/2018 | MECHANICAL - PROGRESS | mramber1 | Approved | |
04/10/2018 | BUILDING PRE-SLAB | mramber1 | Approved | |
04/16/2018 | ELECTRIC - FINAL | mramber1 | Approved | |
04/17/2018 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER CHLORINATION REPORT COMPLETED |
05/07/2018 | MECHANICAL - FINAL | G.PERU | Approved | PER BUILDING FINAL |
05/07/2018 | BUILDING - FINAL | G.PERU | Approved | AIR BALANCE REPORT COMPLETED |