Permit: T17CM04161
Permit Details
Apply Date:
05/25/2017
Applicant:
SHELL, STEVEN COLT
Description:
RESTAURANT
Architects:
- SHELL, STEVEN COLT
Contractors:
- SAVANNAH CONSTRUCTION CO LLC
Permit Reviews
Permit Number - T17CM04161
Permit Status: C of o
Permit Description: RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/31/2019 | REVISION - - 1ST | 01/31/2019 | COMPLETED |
| 05/25/2017 | COMMERCIAL - TI | 05/26/2017 | COMPLETED |
| 05/26/2017 | RESUBMITTAL | 06/13/2017 | COMPLETED |
| 06/13/2017 | RESUBMITTAL | 01/28/2019 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM04161
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/25/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM04161
Permit Description: RESTAURANT
Total Completed Inspections - 32
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/14/2017 | MECHANICAL - HOODS | mramber1 | Approved | 6 front hoods ok smoke test, okto double wrap straight joints |
| 08/28/2017 | FRAMING | mramber1 | Approved | |
| 08/28/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | |
| 08/28/2017 | ELECTRIC - OUTDOOR LIGHTING | mramber1 | Approved | |
| 08/28/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
| 09/01/2017 | SHEET ROCK NAILING | mramber1 | Approved | |
| 02/28/2018 | PLUMBING - GAS PRESSURE TEST | DFLORES2 | Approved | |
| 03/02/2018 | HEALTH DEPT - FINAL 724-7908 | JKINCAID | Approved | |
| 03/07/2018 | PLUMBING - PROGRESS | aquiroz | Approved | |
| 03/21/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | SITE PLAN NOT MATCHEING SITE REFERENCE PLAN. PROVIDE COT AP DP17-0091 PLAN. |
| 03/22/2018 | FIRE - FINAL | CBASALDUA | Approved | |
| 03/22/2018 | FIRE - KITCHEN EXH HOOD FINAL | CBASALDUA | Approved | |
| 03/22/2018 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 03/22/2018 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 03/22/2018 | BUILDING - PROGRESS | mramber1 | Approved | |
| 03/22/2018 | BUILDING ABOVE CEILING | mramber1 | Approved | |
| 03/22/2018 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | |
| 03/22/2018 | ELECTRIC - CONSTRUCTION POWER | mramber1 | Approved | |
| 03/22/2018 | ELECTRIC - TEMP POWER FOR TEST | mramber1 | Approved | |
| 03/22/2018 | ELECTRIC - PROGRESS | mramber1 | Approved | |
| 03/22/2018 | OUTDOOR LIGHTING FINAL | mramber1 | Approved | |
| 03/22/2018 | PLUMBING - ROUGH, SOIL | mramber1 | Approved | |
| 03/22/2018 | PLUMBING - ABOVE CEILING | mramber1 | Approved | |
| 03/22/2018 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
| 03/22/2018 | MECHANICAL - ABOVE CEILING | mramber1 | Approved | |
| 03/26/2018 | PLUMBING - FINAL | mramber1 | Approved | |
| 03/26/2018 | MECHANICAL - FINAL | mramber1 | Approved | |
| 03/27/2018 | CERTIFICATE OF OCCUPANCY | mramber1 | Approved | |
| 03/27/2018 | BUILDING - FINAL | mramber1 | Approved | |
| 03/27/2018 | ELECTRIC - FINAL | mramber1 | Approved | |
| 03/27/2018 | ELECTRIC - UFER | mramber1 | Approved | |
| 03/27/2018 | ELECTRIC - SERVICE UPGRADE | mramber1 | Approved |