Permit: T17CM03949
Permit Details
Status:
C of o
Type:
SINGLE FAMILY NEW
Address:
4748 E SAN FRANCISCO BL
Address NEW:
4748 E SAN FRANCISCO BL
Apply Date:
05/18/2017
Applicant:
HESSE, ANDREW RUDD
Description:
NEW SFR
Architects:
- HESSE, ANDREW RUDD
Contractors:
- HELIOS GROUP LLC
Permit Reviews
Permit Number - T17CM03949
Permit Status: C of o
Permit Description: NEW SFR
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/18/2017 | PLANS OK TO SUBMIT - RES | 05/19/2017 | COMPLETED |
| 05/19/2017 | RESIDENTIAL - BLDG/WWM | 06/02/2017 | COMPLETED |
| 06/13/2017 | RESUBMITTAL | 06/16/2017 | COMPLETED |
| 06/16/2017 | RESUBMITTAL | 07/07/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM03949
Permit Status: C of o
Permit Description: NEW SFR
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/18/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM03949
Permit Description: NEW SFR
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2017 | ELECTRIC - UFER | DQUINN | Approved | |
| 07/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | DQUINN | Approved | |
| 07/25/2017 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | |
| 07/25/2017 | PLUMBING - SEWER HCS CONNECT | TVALENC1 | Approved | |
| 08/04/2017 | PLUMBING - PRE SLAB | TVALENC1 | Approved | |
| 08/04/2017 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | |
| 08/04/2017 | BUILDING PRE-SLAB | TVALENC1 | Approved | |
| 09/14/2017 | PLUMBING - YARD WTR LINE/TEST | JMILITE1 | Approved | IVRS - Inspection :* |
| 10/16/2017 | ROOF NAILING | RGREENE1 | Approved | |
| 10/16/2017 | EXT METAL CLIPS/EXT SHEATHING | RGREENE1 | Approved | |
| 11/01/2017 | ELECTRIC - CONSTRUCTION POWER | ESTEVEN1 | Approved | APPROVED ECO |
| 11/02/2017 | TEP CLEARANCE - AM | ESTEVENS | Approved | ECO |
| 01/18/2018 | PLUMBING - GAS PRESS TEST FNL | NORTH | Approved | |
| 01/18/2018 | MECHANICAL - INTERMEDIATE | NORTH | Approved | |
| 01/18/2018 | PLUMBING - GAS PRESS TEST FNL | NORTH | Approved | |
| 01/18/2018 | ELECTRIC - INTERMEDIATE | NORTH | Approved | |
| 01/18/2018 | U VALUE FOR WINDOW | NORTH | Approved | |
| 01/18/2018 | FRAMING | NORTH | Approved | |
| 01/18/2018 | PLUMBING - GAS PRESSURE TEST | NORTH | Approved | |
| 02/23/2018 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
| 02/23/2018 | STUCCO MESH | TVALENC1 | Approved | IVRS - Inspection :* |
| 03/14/2018 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
| 09/24/2018 | MECHANICAL - FINAL | DFLORES | Approved | |
| 09/24/2018 | PLUMBING - FINAL | DFLORES | Approved | |
| 09/24/2018 | ELECTRIC - FINAL | DFLORES | Approved | |
| 09/24/2018 | BUILDING - FINAL | DFLORES | Approved | |
| 09/26/2018 | GAS CLEARANCE | BNORTH | Approved | |
| 09/26/2018 | MECHANICAL - PROGRESS | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | MECHANICAL - ABOVE CEILING | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | PLUMBING - PROGRESS | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | SITE - SEWER | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | PLUMBING - ABOVE CEILING | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | ELECTRIC - PROGRESS | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | ELECTRIC - ABOVE CEILING | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | BUILDING - PROGRESS | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | BUILDING ABOVE CEILING | DFLORES | Approved | APPROVED PER BUILDING FINAL |
| 09/26/2018 | ELECTRIC - SERVICE UPGRADE | DFLORES | Approved | APPROVED PER BUILDING FINAL |