Permit: T17CM03788
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
3510 N CRAYCROFT RD BLDG#4
Address NEW:
3510 N CRAYCROFT RD BLDG#4
Apply Date:
05/12/2017
Applicant:
N/A
Description:
NEW APARTMENT
Architects:
- ACORN, KIM BRIAN
Contractors:
- CW BUILDERS LLC
Permit Reviews
Permit Number - T17CM03788
Permit Status: C of o
Permit Description: NEW APARTMENT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/08/2018 | REVISION - - 1ST | 04/13/2018 | COMPLETED |
| 05/02/2018 | REVISION - - 2ND | 05/02/2018 | COMPLETED |
| 05/02/2018 | REVISION - - 2ND | 05/30/2018 | COMPLETED |
| 05/12/2017 | PLANS OK TO SUBMIT - COMM | 05/12/2017 | COMPLETED |
| 05/12/2017 | COMMERCIAL - NEW | 06/23/2017 | COMPLETED |
| 06/23/2017 | RESUBMITTAL | 08/02/2017 | COMPLETED |
| 07/11/2018 | REVISION - - 3RD | 07/11/2018 | COMPLETED |
| 07/11/2018 | REVISION - - 3RD | 08/01/2018 | COMPLETED |
| 08/01/2018 | REVISION - - 3RD | 08/22/2018 | COMPLETED |
| 08/02/2017 | RESUBMITTAL | 08/30/2017 | COMPLETED |
| 08/30/2017 | RESUBMITTAL | 03/08/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM03788
Permit Status: C of o
Permit Description: NEW APARTMENT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/12/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM03788
Permit Description: NEW APARTMENT
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/12/2018 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* |
| 08/17/2018 | BUILDING PRE-SLAB | DFLORES2 | Approved | |
| 09/14/2018 | PLUMBING - YARD WTR LINE/TEST | GWest | Approved | PA- Aproved Buildings #4 and #5 Yard water line. Pressure Test, Approved. |
| 09/18/2018 | BUILDING - PROGRESS | DQUINN | Approved | PRE-GROUT FOR STAIR COLUMNS - BLDG. 4 - E., W., + N. COLUMNS OK TO 4', S.W. 2 COLUMNS OK TO 12', S.E. 2 COLUMNS OK TO 8' |
| 11/01/2018 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | North east, north west, and south east stairwell columns OK to grout to top. |
| 11/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | DMCCARTHY | Approved | for CMU column's last course. |
| 11/30/2018 | ELECTRIC - PROGRESS | GWEST | Approved | |
| 12/04/2018 | ROOF NAILING | GWEST | Approved | |
| 12/24/2018 | ELECTRIC - UNDERGROUND | GWEST | Approved | |
| 12/28/2018 | FRAMING | RCHANDLER | Approved | ROOF |
| 03/07/2019 | PLUMBING - INTERMEDIATE | RCHANDLER | Approved | |
| 03/07/2019 | EXT METAL CLIPS/EXT SHEATHING | RCHANDLER | Approved | |
| 04/12/2019 | MECHANICAL - INTERMEDIATE | GWEST | Approved | This is Building 4, Floor 1. |
| 04/12/2019 | ELECTRIC - INTERMEDIATE | GWEST | Approved | This is Building 4, Floor 1. |
| 06/04/2019 | TEP CLEARANCE - PM | RCHANDLER | Approved | Unit numbers 4310, 4301, 4309, 4210, 4303, 4209, 4302, 4203, 4202, 4103, 4201, 4102, 4110, 4101, 4109, HP, 4104, 4108, 4105, 4204, 4106, 4205, 4107, 4206, 4207, 4208, 4306, 4304, 4307, 4305, 4308. CODE ECO |
| 06/04/2019 | ELECTRIC - SERVICE UPGRADE | RCHANDLER | Approved | Clearance ECO. Unit numbers 4310, 4301, 4309, 4210, 4303, 4209, 4302, 4203, 4202, 4103, 4201, 4102, 4110, 4101, 4109, HP, 4104, 4108, 4105, 4204, 4106, 4205, 4107, 4206, 4207, 4208, 4306, 4304, 4307, 4305, 4308. |
| 06/24/2019 | PLUMBING - ROOF DRAINS | MRAMBER | Approved | |
| 08/09/2019 | MECHANICAL - FINAL | MRAMBER | Approved | |
| 08/09/2019 | ELECTRIC - FINAL | MRAMBER | Approved | |
| 08/19/2019 | PLUMBING - FINAL | RSHERRY | Approved | REVIEW OF WATER DISINFECTION REPORT COMPLETE |
| 08/20/2019 | FIRE - FINAL | MRoss | Approved | Provide clearance around riser through concrete by completion of project |
| 08/20/2019 | FIRE - ALARM FINAL | MRoss | Approved | |
| 08/20/2019 | FIRE SPKLR - FINAL | MRoss | Approved | Provide clearance around riser through concrete by completion of project |
| 08/22/2019 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 08/27/2019 | BUILDING - FINAL | JGARCIA1 | Approved | Engineering and FIre Finals have been approved. Chlorination and Air Balance reports have been reviewed. |
| 08/27/2019 | ELECTRIC - CONSTRUCTION POWER | JGARCIA1 | Approved | |
| 08/27/2019 | MECHANICAL - ABOVE CEILING | JGARCIA1 | Approved | |
| 08/27/2019 | MECHANICAL - PROGRESS | JGARCIA1 | Approved | |
| 08/27/2019 | BUILDING ABOVE CEILING | JGARCIA1 | Approved | |
| 08/27/2019 | STUCCO MESH | JGARCIA1 | Approved | |
| 08/27/2019 | U VALUE FOR WINDOW | JGARCIA1 | Approved | |
| 08/27/2019 | SHEET ROCK NAILING | JGARCIA1 | Approved | |
| 08/27/2019 | ELECTRIC - UFER | JGARCIA1 | Approved | |
| 08/27/2019 | ELECTRIC - ABOVE CEILING | JGARCIA1 | Approved | |
| 08/27/2019 | PLUMBING - PRE SLAB | JGARCIA1 | Approved | |
| 08/27/2019 | PLUMBING - ABOVE CEILING | JGARCIA1 | Approved | |
| 08/27/2019 | PLUMBING - PROGRESS | JGARCIA1 | Approved |