| 08/22/2019 |
ENGINEERING - FINAL |
|
Approved |
|
| 08/16/2019 |
ENGINEERING - FINAL |
|
Partial Approval |
FINAL NOT TO BE GIVEN TILL ALL CONSTRUCTION FENCE MATERIAL HAS BEEN REARRANGED BETWEEN BUILDINGS #4 AND #5 TO PREVENT THE ENTRANCE OF THE GENERAL PUBLIC INTO THE CONSTRUCTION ZONES. |
| 08/14/2019 |
ENGINEERING - FINAL |
|
Continued |
FINAL FOR THIS ITEM WILL BE SCHEDULED FOR 8/16/19. CURRENTLY MOST OF THE ADJACENT SIT IS COMPLETE, MINOR ADJUSTMENT TO A RETAINING WALL AND THE BACKFILL BETWEEN THE WALL AND THE SIDEWALK FOR BUILDING #5. |
| 08/09/2019 |
ENGINEERING - FINAL |
|
Not ready for Inspection |
GC said all inspections have been completed but landscaping no history to back that up calling back in on Monday. |