Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Address NEW:
10210 E GOLF LINKS RD
Apply Date:
04/03/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL
Contractors:
  • CORSTONE CONTRACTORS LLC

Permit Reviews

Permit Number - T17CM02528
Permit Status: Final
Permit Description: RETAIL
Start Date Submittal Complete Date Status  
01/24/2018 REVISION - - 1ST 01/24/2018 COMPLETED Review Details
01/24/2018 REVISION - - 1ST 02/13/2018 COMPLETED Review Details
04/03/2017 PLANS OK TO SUBMIT - COMM 04/03/2017 COMPLETED Review Details
04/03/2017 COMMERCIAL - NEW 05/12/2017 COMPLETED Review Details
05/12/2017 RESUBMITTAL - TI ALL 05/30/2017 COMPLETED Review Details
05/30/2017 RESUBMITTAL 09/25/2017 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM02528
Permit Status: Final
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
Date Name
04/03/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T17CM02528
Permit Description: RETAIL
Total Completed Inspections - 38
Date Description Inspector Results Comments
12/04/2017 CERTIFICATE OF OCCUPANCY ENEWCOMB Approved P2I MAY BE DELETED WHEN THE ROOF/FLOOR TRUSS DESIGN CALCULATIONS AND DRAWINGS HAVE BEEN REVIEWED AND APPROVED.
12/05/2017 ELECTRIC - UFER BBENEDO1 Approved IVRS - Inspection :*
12/05/2017 EXCAVATION/LAYOUT REBAR & ZON BBENEDO1 Approved IVRS - Inspection :*
12/13/2017 PLUMBING - YARD WTR LINE/TEST RGREENE1 Approved
12/13/2017 PLUMBING - ROUGH, SOIL RGREENE1 Approved
12/14/2017 BUILDING PRE-SLAB RGREENE1 Approved
12/14/2017 ELECTRIC - UNDERGROUND RGREENE1 Approved
12/14/2017 PLUMBING - PRE SLAB RGREENE1 Approved
12/22/2017 STEM WALL/RETAINING WALL RGREENE1 Approved 2ND LIFT
12/29/2017 BUILDING - PROGRESS BBENEDO1 Approved IVRS - Inspection :*
01/10/2018 PLUMBING - INTERMEDIATE BBENEDO1 Approved IVRS - Inspection :*
01/12/2018 ROOF NAILING DFLORES2 Approved
01/17/2018 STUCCO MESH BBENEDO1 Approved IVRS - Inspection :*
01/17/2018 EXT METAL CLIPS/EXT SHEATHING BBENEDO1 Approved IVRS - Inspection :*
01/18/2018 SHEET ROCK NAILING BBENEDO1 Approved IVRS - Inspection :*
01/19/2018 FRAMING BBENEDO1 Approved IVRS - Inspection :*
01/30/2018 TEP CLEARANCE - AM RGREENE Approved ECO
01/30/2018 ELECTRIC - CONSTRUCTION POWER RGREENE1 Approved
02/15/2018 MECHANICAL - FINAL RGREENE1 Approved
02/15/2018 PLUMBING - FINAL RGREENE1 Approved
02/15/2018 ELECTRIC - FINAL RGREENE1 Approved
02/21/2018 FIRE - FINAL CBASALDUA Approved
02/22/2018 U VALUE FOR WINDOW DQUINN Approved
02/22/2018 BUILDING ABOVE CEILING DQUINN Approved
02/22/2018 MECHANICAL - PROGRESS DQUINN Approved
02/22/2018 MECHANICAL - ABOVE CEILING DQUINN Approved
02/22/2018 PLUMBING - PROGRESS DQUINN Approved
02/22/2018 SITE - SEWER DQUINN Approved
02/22/2018 PLUMBING - ABOVE CEILING DQUINN Approved
02/22/2018 ELECTRIC - PROGRESS DQUINN Approved
02/22/2018 ELECTRIC - ABOVE CEILING DQUINN Approved
02/22/2018 ELECTRIC - INTERMEDIATE DQUINN Approved
02/22/2018 MECHANICAL - INTERMEDIATE DQUINN Approved
02/22/2018 PLUMBING - GAS PRESSURE TEST DQUINN Approved
02/22/2018 BUILDING - FINAL DQUINN Approved PENDING WATER CHLORINATION REPORT
02/22/2018 BUILDING - FINAL RSHERRY Approved REVIEW OF WATER CHLORINATION REPORT COMPLETE
02/22/2018 ELECTRIC - SERVICE UPGRADE DQUINN Approved
02/23/2018 ENGINEERING - FINAL MRUSSO Approved