Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T17CM02522
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4343 N ORACLE RD #189
Address NEW:
4343 N ORACLE RD #189
Apply Date:
04/03/2017
Applicant:
N/A
Description:
TI: OFFICE
Architects:
- JEFFREY H SHINKLE
Contractors:
- AMERICAN RETAIL CONTRACTORS LLC
Permit Reviews
Permit Number - T17CM02522
Permit Status: C of o
Permit Description: TI: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/03/2017 | PLANS OK TO SUBMIT - COMM | 04/03/2017 | COMPLETED |
| 04/03/2017 | COMMERCIAL - TI | 05/03/2017 | COMPLETED |
| 05/11/2017 | RESUBMITTAL - TI ALL | 05/16/2017 | COMPLETED |
| 05/16/2017 | RESUBMITTAL | 05/17/2017 | COMPLETED |
| 05/17/2017 | RESUBMITTAL | 05/18/2017 | COMPLETED |
| 05/18/2017 | RESUBMITTAL | 05/18/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM02522
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/03/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM02522
Permit Description: TI: OFFICE
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2017 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 06/02/2017 | FRAMING | JBURGE | Approved | |
| 06/05/2017 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | |
| 06/07/2017 | PLUMBING - PROGRESS | BSTEVENS | Approved | |
| 06/07/2017 | SHEET ROCK NAILING | BSTEVENS | Approved | |
| 06/08/2017 | BUILDING ABOVE CEILING | JBURGE | Approved | |
| 06/13/2017 | ELECTRIC - PROGRESS | BSTEVENS | Approved | |
| 06/13/2017 | BUILDING - PROGRESS | BSTEVENS | Approved | |
| 06/15/2017 | MECHANICAL - ABOVE CEILING | NORTH | Approved | |
| 06/15/2017 | PLUMBING - INTERMEDIATE | NORTH | Approved | |
| 06/15/2017 | ELECTRIC - ABOVE CEILING | NORTH | Approved | |
| 06/20/2017 | FIRE SPKLR - FINAL | jdonovan | Approved | |
| 06/21/2017 | ELECTRIC - FINAL | BSTEVENS | Approved | |
| 06/21/2017 | PLUMBING - ABOVE CEILING | BSTEVENS | Approved | |
| 06/21/2017 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
| 06/22/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 06/23/2017 | MECHANICAL - FINAL | bstevens | Approved | |
| 06/23/2017 | PLUMBING - FINAL | bstevens | Approved | |
| 06/23/2017 | CERTIFICATE OF OCCUPANCY | bstevens | Approved | |
| 06/23/2017 | BUILDING - FINAL | bstevens | Approved | |
| 06/23/2017 | MECHANICAL - FINAL | BSTEVENS | Approved | ALL FINALS PENDING AIR BALANCE AND CHLORINATION APPROVAL BY COT REVIEWER. |
| 06/23/2017 | PLUMBING - FINAL | BSTEVENS | Approved | ALL FINALS PENDING AIR BALANCE AND CHLORINATION APPROVAL BY COT REVIEWER. |
| 06/23/2017 | CERTIFICATE OF OCCUPANCY | BSTEVENS | Approved | ALL FINALS PENDING AIR BALANCE AND CHLORINATION APPROVAL BY COT REVIEWER. |
| 06/23/2017 | BUILDING - FINAL | BSTEVENS | Approved | ALL FINALS PENDING AIR BALANCE AND CHLORINATION APPROVAL BY COT REVIEWER. |
| 06/26/2017 | ENGINEERING - FINAL | MRUSSO | Approved |