Permit Reviews
Permit Number - T17CM02151
Permit Status: L of c
Permit Description: TI: CHARTER SCHOOL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/17/2017 | PLANS OK TO SUBMIT - COMM | 03/17/2017 | COMPLETED |
03/17/2017 | COMMERCIAL - TI | 04/24/2017 | COMPLETED |
04/25/2017 | RESUBMITTAL - TI ALL | 05/22/2017 | COMPLETED |
05/22/2017 | RESUBMITTAL | 05/24/2017 | COMPLETED |
10/31/2017 | REVISION - - 1ST | 07/20/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM02151
Permit Status: L of c
Permit Description: TI: CHARTER SCHOOL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/17/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T17CM02151
Permit Description: TI: CHARTER SCHOOL
Total Completed Inspections - 33
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/12/2017 | ELECTRIC - UFER | DQUINN | Approved | |
06/19/2017 | ELECTRIC - UNDERGROUND | ESTEVEN1 | Approved | FROM EAST BUILDING TO WEST BUILDING AROUND TO SWITCH GEAR LOCATION AT REAR, OK TO COVER. |
06/26/2017 | REINFORCED MASONRY PRE-GROUT | DQUINN | Approved | NORTH COLUMNS OK TO GROUT TO TOP |
07/10/2017 | ELECTRIC - CONSTRUCTION POWER | ESTEVEN1 | Approved | APPROVED. |
07/10/2017 | ELECTRIC - TEMPORARY SERVICE | ESTEVEN1 | Approved | APPROVED. |
07/31/2017 | ELECTRIC - PROGRESS | ESTEVEN1 | Approved | APPROVED. |
07/31/2017 | BUILDING - PROGRESS | ESTEVEN1 | Approved | APPROVED. |
07/31/2017 | U VALUE FOR WINDOW | ESTEVEN1 | Approved | APPROVED. |
07/31/2017 | EXT METAL CLIPS/EXT SHEATHING | ESTEVEN1 | Approved | APPROVED. |
07/31/2017 | PLUMBING - PROGRESS | ESTEVEN1 | Approved | APPROVED. |
07/31/2017 | PLUMBING - ROUGH, SOIL | ESTEVEN1 | Approved | APPROVED. |
08/01/2017 | BUILDING PRE-SLAB | ESTEVEN1 | Approved | APPROVED |
08/01/2017 | STUCCO MESH | ESTEVEN1 | Approved | |
08/01/2017 | ROOF NAILING | ESTEVEN1 | Approved | |
08/01/2017 | PLUMBING - YARD WTR LINE/TEST | ESTEVEN1 | Approved | |
10/11/2017 | FIRE - FINAL | CBASALDUA | Approved | |
10/11/2017 | BUILDING - FINAL | ESTEVENS | Approved | PENDING OTHER INSPECTIONS |
11/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | |
11/13/2017 | ELECTRIC - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
11/13/2017 | FRAMING | ESTEVEN1 | Approved | APPROVED |
11/14/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
11/30/2017 | ELECTRIC - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
11/30/2017 | BUILDING ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
11/30/2017 | MECHANICAL - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
11/30/2017 | MECHANICAL - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
11/30/2017 | PLUMBING - ABOVE CEILING | ESTEVEN1 | Approved | APPROVED |
11/30/2017 | PLUMBING - INTERMEDIATE | ESTEVEN1 | Approved | APPROVED |
12/20/2017 | OUTDOOR LIGHTING FINAL | ESTEVEN1 | Approved | APPROVED |
12/20/2017 | ELECTRIC - OUTDOOR LIGHTING | ESTEVEN1 | Approved | APPROVED |
12/20/2017 | ELECTRIC - FINAL | ESTEVEN1 | Approved | APPROVED |
12/20/2017 | MECHANICAL - FINAL | ESTEVEN1 | Approved | PENDING AIR BALANCE REPORT |
12/20/2017 | PLUMBING - FINAL | ESTEVEN1 | Approved | PENDING WATER REPORT |
12/28/2017 | ENGINEERING - FINAL | MRUSSO | Approved |