Permit: T17CM01719
Permit Details
Apply Date:
03/03/2017
Applicant:
LAND DEVELOPMENT CONSULTANTS LLC
Description:
NEW RESTAURANT/POPEYES
Architects:
- WINDLE, DAVID SCOTT
Contractors:
- MC MANUS CONSTRUCTION LLC
Permit Reviews
Permit Number - T17CM01719
Permit Status: C of o
Permit Description: NEW RESTAURANT/POPEYES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/03/2017 | PLANS OK TO SUBMIT - COMM | 03/03/2017 | COMPLETED |
| 03/03/2017 | COMMERCIAL - NEW | 03/29/2017 | COMPLETED |
| 04/07/2017 | RESUBMITTAL | 04/10/2017 | COMPLETED |
| 04/10/2017 | RESUBMITTAL | 04/19/2017 | COMPLETED |
| 04/19/2017 | WALK THRU - COMM | 04/19/2017 | COMPLETED |
| 04/19/2017 | OTHER | 05/19/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM01719
Permit Status: C of o
Permit Description: NEW RESTAURANT/POPEYES
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/03/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM01719
Permit Description: NEW RESTAURANT/POPEYES
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2017 | SITE - SEWER | benedon | Approved | |
| 06/16/2017 | PLUMBING - ROUGH, SOIL | benedon | Approved | |
| 06/22/2017 | BUILDING PRE-SLAB | bbenedo | Approved | |
| 06/28/2017 | PLUMBING - PRE SLAB | bbenedon | Approved | letter fof trap gaurds 6/22/17 |
| 07/05/2017 | PLUMBING - YARD WTR LINE/TEST | bbenedo1 | Approved | |
| 07/06/2017 | EXT METAL CLIPS/EXT SHEATHING | bbenedon | Approved | |
| 07/06/2017 | ROOF NAILING | bbenedon | Approved | |
| 07/17/2017 | ELECTRIC - INTERMEDIATE | bbenedon | Approved | |
| 07/17/2017 | PLUMBING - INTERMEDIATE | bbenedon | Approved | |
| 07/17/2017 | PLUMBING - ROOF DRAINS | bbenedon | Approved | |
| 07/17/2017 | MECHANICAL - INTERMEDIATE | bbenedon | Approved | |
| 07/24/2017 | FRAMING | BBENEDO1 | Approved | IVRS - Inspection :* |
| 07/25/2017 | SHEET ROCK NAILING | bbenedon | Approved | |
| 08/09/2017 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDO1 | Approved | IVRS - Inspection :* |
| 08/09/2017 | MECHANICAL - HOODS | BBENEDO1 | Approved | IVRS - Inspection :* |
| 08/22/2017 | TEP CLEARANCE - AM | BBENEDON | Approved | ECO |
| 08/23/2017 | PLUMBING - GAS PRESS TEST FNL | BBENEDO1 | Approved | IVRS - Inspection :* |
| 08/23/2017 | PLUMBING - GAS PRESSURE TEST | BBENEDO1 | Approved | IVRS - Inspection :* |
| 08/24/2017 | GAS CLEARANCE | BBENEDON | Approved | |
| 08/24/2017 | ELECTRIC - UNDERGROUND | bbenedon | Approved | |
| 08/24/2017 | ELECTRIC - ABOVE CEILING | bbenedon | Approved | |
| 08/24/2017 | ELECTRIC - CONSTRUCTION POWER | bbenedon | Approved | |
| 08/24/2017 | ELECTRIC - PROGRESS | bbenedon | Approved | |
| 08/24/2017 | PLUMBING - ABOVE CEILING | bbenedon | Approved | |
| 08/24/2017 | PLUMBING - PROGRESS | bbenedon | Approved | |
| 08/24/2017 | MECHANICAL - ABOVE CEILING | bbenedon | Approved | |
| 08/24/2017 | MECHANICAL - PROGRESS | bbenedon | Approved | |
| 08/25/2017 | FIRE - KITCHEN EXH HOOD FINAL | jdonovan | Approved | |
| 08/28/2017 | U VALUE FOR WINDOW | bbenedon | Approved | |
| 08/28/2017 | BUILDING - PROGRESS | bbenedon | Approved | |
| 08/28/2017 | ELECTRIC - UFER | bbenedon | Approved | |
| 08/28/2017 | ELECTRIC - OUTDOOR LIGHTING | bbenedon | Approved | |
| 08/28/2017 | BUILDING ABOVE CEILING | bbenedon | Approved | |
| 09/05/2017 | FIRE - FINAL | jvincent | Approved | will add/mount occ load sign |
| 09/05/2017 | FIRE - FINAL | jvincent | Approved | Needs the following two operational permits. 1) Places of assembly 2) Combustible liquids for cooking oil tank outside 3) CO2 operational permit and alarm required if bulk CO2 tank is placed in service. |
| 09/08/2017 | MECHANICAL - FINAL | bnbenedon | Approved | Complete all work; Signs, Mop sink soap disp, air gaps, seal piping penetrations, uv protection. Air bal report to RWS |
| 09/08/2017 | PLUMBING - FINAL | bnbenedon | Approved | Complete all work; Signs, Mop sink soap disp, air gaps, seal piping penetrations, uv protection. Air bal report to RWS |
| 09/08/2017 | ELECTRIC - FINAL | bnbenedon | Approved | Complete all work; Signs, Mop sink soap disp, air gaps, seal piping penetrations, uv protection. Air bal report to RWS |
| 09/08/2017 | BUILDING - FINAL | bnbenedon | Approved | Complete all work; Signs, Mop sink soap disp, air gaps, seal piping penetrations, uv protection. Air bal report to RWS |
| 09/12/2017 | NPPO - FINAL | MRUSSO1 | Approved | |
| 09/12/2017 | SIGN - FINAL | MRUSSO1 | Approved | |
| 09/12/2017 | LANDSCAPE - FINAL | MRUSSO1 | Approved | |
| 09/12/2017 | ENGINEERING - FINAL | MRUSSO1 | Approved | |
| 09/13/2017 | RIGHT OF WAY - FINAL | JKokot | Approved | No work done in ROW |