Permit: T17CM01474
Permit Details
Apply Date:
02/23/2017
Applicant:
ROBERT CAYLOR CONSTRUCTION COMPANY
Description:
APARTMENTS 4TH FLOOR
Contractors:
- CAYLOR CONSTRUCTION COMPANY , RO*** APA ***
- ROBERT CAYLOR CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T17CM01474
Permit Status: C of o
Permit Description: APARTMENTS 4TH FLOOR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/23/2017 | PLANS OK TO SUBMIT - COMM | 02/28/2017 | COMPLETED |
02/28/2017 | COMMERCIAL - TI | 03/20/2017 | COMPLETED |
03/27/2017 | RESUBMITTAL - TI ALL | 04/18/2017 | COMPLETED |
04/18/2017 | RESUBMITTAL | 04/18/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM01474
Permit Status: C of o
Permit Description: APARTMENTS 4TH FLOOR
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/23/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM01474
Permit Description: APARTMENTS 4TH FLOOR
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/17/2017 | RIGHT OF WAY - FINAL | DR | Approved | |
06/02/2017 | ENGINEERING - FINAL | MRUSSO | Approved | |
06/02/2017 | SIGN - FINAL | MRUSSO | Approved | |
06/02/2017 | LANDSCAPE - FINAL | MRUSSO | Approved | |
06/19/2017 | ELECTRIC - SERVICE UPGRADE | mramber1 | Approved | |
06/19/2017 | ELECTRIC - UFER | mramber1 | Approved | |
06/28/2017 | PLUMBING - GAS PRESS TEST FNL | mramber1 | Approved | no appliances at this time |
06/28/2017 | PLUMBING - PROGRESS | mramber1 | Approved | W/C flanges ok |
07/03/2017 | NPPO - FINAL | MRUSSO | Approved | |
07/10/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | ECO #401 THRU 405 |
07/12/2017 | BUILDING ABOVE CEILING | mramber1 | Approved | |
07/12/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | |
07/12/2017 | PLUMBING - GAS PRESSURE TEST | mramber1 | Approved | |
07/12/2017 | MECHANICAL - ABOVE CEILING | mramber1 | Approved | |
07/14/2017 | FRAMING | mramber1 | Approved | |
07/14/2017 | BUILDING - PROGRESS | mramber1 | Approved | |
07/14/2017 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
07/14/2017 | MECHANICAL - PROGRESS | mramber1 | Approved | |
07/24/2017 | SHEET ROCK NAILING | mramber1 | Approved | |
07/24/2017 | ELECTRIC - FINAL | mramber1 | Approved | |
07/24/2017 | PLUMBING - ABOVE CEILING | mramber1 | Approved | |
07/24/2017 | PLUMBING - FINAL | mramber1 | Approved | |
07/24/2017 | MECHANICAL - FINAL | mramber1 | Approved | |
10/05/2017 | FIRE - FINAL | GDAURIA | Approved | |
10/05/2017 | ELECTRIC - PROGRESS | AQUIROZ | Approved | |
10/05/2017 | BUILDING - FINAL | AQUIROZ | Approved |