Permit: T17CM00706
Permit Details
Apply Date:
01/27/2017
Applicant:
BRIGHT, RICK LANE
Description:
OFFICE
Architects:
- BRIGHT, RICK LANE
Contractors:
- BARKER MORRISSEY CONTRACTING INC **APA**
Permit Reviews
Permit Number - T17CM00706
Permit Status: C of o
Permit Description: OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/27/2017 | COMMERCIAL - TI | 01/30/2017 | COMPLETED |
| 01/30/2017 | RESUBMITTAL | 05/01/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM00706
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/27/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM00706
Permit Description: OFFICE
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/26/2017 | PLUMBING - ROUGH, SOIL | JJaworsky | Approved | OK to backfill |
| 07/14/2017 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | |
| 07/14/2017 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 07/14/2017 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 07/14/2017 | FRAMING | DQUINN | Approved | |
| 07/19/2017 | SHEET ROCK NAILING | ESTEVEN1 | Approved | APPROVED |
| 08/01/2017 | ELECTRIC - SERVICE UPGRADE | BSTEVENS | Approved | |
| 08/01/2017 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | |
| 08/03/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | INCR |
| 09/07/2017 | CERTIFICATE OF OCCUPANCY | QUINN | Approved | FIRE AND ENGINEERING HAVE BEEN APPROVED SO WE CAN APPROVE C OF O. PER D.QUINN. |
| 09/07/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 09/07/2017 | CERTIFICATE OF OCCUPANCY | DQUINN | Approved | OK FOR C OF O WHEN FIRE AND ENGINEERING SIGN OFF |
| 09/07/2017 | BUILDING - PROGRESS | DQUINN | Approved | |
| 09/07/2017 | BUILDING - FINAL | DQUINN | Approved | |
| 09/07/2017 | ELECTRIC - ABOVE CEILING | DQUINN | Approved | |
| 09/07/2017 | ELECTRIC - FINAL | DQUINN | Approved | |
| 09/07/2017 | PLUMBING - ABOVE CEILING | DQUINN | Approved | |
| 09/07/2017 | PLUMBING - PROGRESS | DQUINN | Approved | |
| 09/07/2017 | PLUMBING - FINAL | DQUINN | Approved | |
| 09/07/2017 | MECHANICAL - ABOVE CEILING | DQUINN | Approved | |
| 09/07/2017 | MECHANICAL - FINAL | DQUINN | Approved | |
| 09/07/2017 | STUCCO MESH | DQUINN | Approved | |
| 09/07/2017 | BUILDING ABOVE CEILING | DQUINN | Approved | |
| 09/08/2017 | GAS CLEARANCE | QUINN | Approved | |
| 09/08/2017 | ENGINEERING - FINAL | MRUSSO | Approved |