Permit: T16CM09237
Permit Details
Apply Date:
12/09/2016
Applicant:
PINAL DESIGN GROUP LLC
Description:
OFFICE
Contractors:
- S B C GENERAL CONTRACTORS INC ,
Permit Reviews
Permit Number - T16CM09237
Permit Status: C of o
Permit Description: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
12/09/2016 | COMMERCIAL - TI | 12/21/2016 | COMPLETED |
12/21/2016 | RESUBMITTAL | 12/27/2016 | COMPLETED |
12/27/2016 | RESUBMITTAL | 12/28/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM09237
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/09/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM09237
Permit Description: OFFICE
Total Completed Inspections - 18
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/04/2017 | PLUMBING - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
01/04/2017 | PLUMBING - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
01/04/2017 | PLUMBING - ROUGH, SOIL | TVALENC1 | Approved | IVRS - Inspection :* |
01/05/2017 | FRAMING | JMILITE1 | Approved | REMOVE SCREWS FROM T-BAR. |
01/18/2017 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
01/18/2017 | BUILDING ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
01/25/2017 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
01/25/2017 | MECHANICAL - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
01/25/2017 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
01/25/2017 | PLUMBING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
01/25/2017 | ELECTRIC - ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
01/25/2017 | BUILDING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
02/01/2017 | FIRE - FINAL | jvincent | Approved | will buy new extinguisher or service existing. |
02/01/2017 | ENGINEERING - FINAL | RLEDONNE | Approved | NO WORK OUT SIDE BUILDING PER AP PLANS. |
02/02/2017 | PLUMBING - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
02/02/2017 | ELECTRIC - FINAL | TVALENC1 | Approved | IVRS - Inspection :* |
02/06/2017 | MECHANICAL - FINAL | MRAMBER | Approved | |
02/06/2017 | BUILDING - FINAL | MRAMBER | Approved | OK FOR C OF O. PER T.VALENCIA |