Permit: T16CM07316
Permit Details
Apply Date:
09/22/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
OFFICE
Contractors:
- D L WITHERS CONSTRUCTION LC
Permit Reviews
Permit Number - T16CM07316
Permit Status: C of o
Permit Description: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/13/2017 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 05/23/2017 | COMPLETED |
05/23/2017 | COMMERCIAL - TI | 06/21/2017 | COMPLETED |
09/05/2017 | REVISION - - 1ST | 09/05/2017 | COMPLETED |
09/22/2016 | PLANS OK TO SUBMIT - COMM | 04/13/2017 | COMPLETED |
11/29/2017 | REVISION - - 2ND | 11/29/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM07316
Permit Status: C of o
Permit Description: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/22/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM07316
Permit Description: OFFICE
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/08/2017 | BUILDING PRE-SLAB | mramber1 | Approved | |
09/20/2017 | REINFORCED MASONRY PRE-GROUT | RCAMACHO | Approved | 2ND LIFT ONLY IN BASEMENT |
09/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | mramber1 | Approved | cap at elevator base ok to pour |
10/16/2017 | ELECTRIC - UNDERGROUND | mramber1 | Approved | |
10/16/2017 | ELECTRIC - FINAL | mramber1 | Approved | no work |
10/26/2017 | MECHANICAL - HYDRONIC PIPING | NORTH | Approved | 3035 HEAT PUMP CONDENSATE DRAIN OK |
11/03/2017 | TEP CLEARANCE - AM | MRAMBER | Approved | INCR |
11/03/2017 | ELECTRIC - PROGRESS | mramber1 | Approved | incr clearence |
11/13/2017 | BUILDING - PROGRESS | RCAMACHO | Approved | 1ST AND 2ND FLOOR ELEVATOR SHAFT WALLS 3RD FLOOR TO 8' HEIGHT ONLY |
11/22/2017 | GAS CLEARANCE | MRAMBER | Approved | |
11/22/2017 | PLUMBING - INTERMEDIATE | mramber1 | Approved | gas connect ok |
12/01/2017 | SHEET ROCK NAILING | mramber1 | Approved | ok to proceed with elevator shaft walls |
12/06/2017 | ELECTRIC - INTERMEDIATE | mramber1 | Approved | 3rd floor panels ok |
12/08/2017 | FRAMING | mramber1 | Approved | 3rd floor interior elevator shaft sheetrock ok |
12/12/2017 | ELECTRIC - ABOVE CEILING | mramber1 | Approved | all fire inspections through F.D. |
01/17/2018 | OUTDOOR LIGHTING FINAL | mramber1 | Approved | |
01/17/2018 | ELECTRIC - OUTDOOR LIGHTING | mramber1 | Approved | |
01/17/2018 | PLUMBING - FINAL | mramber1 | Approved | |
01/31/2018 | MECHANICAL - FINAL | mramber1 | Approved | |
02/07/2018 | ENGINEERING - FINAL | DROBERTS | Approved | |
02/16/2018 | BUILDING ABOVE CEILING | mramber1 | Approved | |
02/16/2018 | MECHANICAL - INTERMEDIATE | mramber1 | Approved | |
02/16/2018 | ELECTRIC - UFER | mramber1 | Approved | |
02/16/2018 | ELECTRIC - CONSTRUCTION POWER | mramber1 | Approved | |
02/16/2018 | ELECTRIC - TEMPORARY SERVICE | mramber1 | Approved | |
02/22/2018 | CERTIFICATE OF OCCUPANCY | mramber1 | Approved | |
02/22/2018 | BUILDING - FINAL | mramber1 | Approved | FIRE APP |
02/22/2018 | FIRE - FINAL | JMPD | Approved |