Inspection History Details
Inspection Status: Approved
Inspection History: SHEET ROCK NAILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/23/2018 | SHEET ROCK NAILING | Approved | ||
| 01/19/2018 | SHEET ROCK NAILING | Partial Approval | FIREWALL JOINT STAGGER OK TO PROCEED | |
| 12/01/2017 | SHEET ROCK NAILING | Partial Approval | ok to proceed with elevator shaft walls | |
| 11/15/2017 | SHEET ROCK NAILING | Partial Approval | 3rd floor , elevator shafts exterior ok, provide verification of interior at floor penetrations | |
| 11/13/2017 | SHEET ROCK NAILING | Partial Approval | 1ST AND 2ND FLOOR ELEVATOR SHAFT WALLS 3RD FLOOR TO 8' HEIGHT ONLY |
|
| 11/06/2017 | SHEET ROCK NAILING | Partial Approval | elevator control walls ok |