Permit: T16CM03553
Permit Details
Apply Date:
05/11/2016
Applicant:
PETE AT APN BUILDERS
Description:
NEW SELF STORAGE BLDG
Architects:
- PAGE, ROBERT ELWOOD
Contractors:
- A P N BUILDERS INC ,
Permit Reviews
Permit Number - T16CM03553
Permit Status: C of o
Permit Description: NEW SELF STORAGE BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/11/2016 | PLANS OK TO SUBMIT - COMM | 05/11/2016 | COMPLETED |
| 05/11/2016 | COMMERCIAL - NEW | 06/20/2016 | COMPLETED |
| 06/30/2016 | RESUBMITTAL | 07/05/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM03553
Permit Status: C of o
Permit Description: NEW SELF STORAGE BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/11/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM03553
Permit Description: NEW SELF STORAGE BLDG
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2016 | REINFORCED MASONRY PRE-GROUT | BSTEVENS | Approved | CHANGED BY BSTEVENS FROM AP TO PA TO ALLOW FOR FUTURE INSPECTIONS. |
| 11/17/2016 | FRAMING | BSTEVENS | Approved | IN BASEMENT FRAMING OK |
| 11/21/2016 | BUILDING PRE-SLAB | TVALENC1 | Approved | IVRS - Inspection :* 1- SOUTH FLOOR SECTION AROUND THE ELEVATOR SHAFT IS OKAY FOR CONCRETE. |
| 12/21/2016 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | EAST AND NORTH FOOTINGS OK TO POUR |
| 12/22/2016 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | OK TO GROUT RETAINING WALL EAST SIDE OF PROPERTY |
| 12/29/2016 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | WIRING AND LIGHTING IN BASEMENT OK. |
| 01/31/2017 | FIRE SPKLR - UG PIPING FLUSH | CBASALDUA | Approved | |
| 01/31/2017 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDUA | Approved | |
| 03/01/2017 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | |
| 03/01/2017 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | |
| 03/02/2017 | TEP CLEARANCE - AM | BSTEVENS | Approved | TMPP |
| 03/26/2017 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
| 03/26/2017 | ROOF NAILING | JBURGE | Approved | |
| 03/26/2017 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | |
| 03/30/2017 | SHEET ROCK NAILING | BSTEVENS | Approved | |
| 04/21/2017 | STUCCO MESH | NORTH | Approved | |
| 05/12/2017 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | |
| 05/12/2017 | ELECTRIC - PROGRESS | JBURGE | Approved | ALL INTERIOR LIGHTING, WIRES FOR EXTERIOR HAS BEEN PULLED (NEED TO LABEL PANELS "A" AND "M" |
| 06/12/2017 | MECHANICAL - INTERMEDIATE | BSTEVENS | Approved | |
| 06/12/2017 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
| 06/12/2017 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved | |
| 06/12/2017 | ELECTRIC - ABOVE CEILING | BSTEVENS | Approved | |
| 06/12/2017 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | |
| 06/12/2017 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 06/12/2017 | BUILDING - PROGRESS | BSTEVENS | Approved | |
| 06/12/2017 | FIREWALL/FIREBARRIER/FIRESTOP | BSTEVENS | Approved | |
| 06/12/2017 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
| 06/12/2017 | BUILDING ABOVE CEILING | BSTEVENS | Approved | |
| 06/13/2017 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 06/13/2017 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDUA | Approved | |
| 07/20/2017 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 07/31/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 08/01/2017 | ELECTRIC - FINAL | ESTEVEN1 | Approved | APPROVED |
| 08/03/2017 | BUILDING - FINAL | estevens | Approved | |
| 08/03/2017 | ENGINEERING - FINAL | pyg | Approved | Cert letter in SIRE under DP15-0117 |
| 08/03/2017 | MECHANICAL - FINAL | bstevens | Approved | completed by rsherry |
| 08/03/2017 | PLUMBING - FINAL | bstevens | Approved | report completed by rsherry |