| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/15/2016 | COMMERCIAL - TI | 03/16/2016 | COMPLETED |
| 03/16/2016 | COMMERCIAL - TI | 04/21/2016 | COMPLETED |
| 04/21/2016 | RESUBMITTAL | 04/22/2016 | COMPLETED |
| 04/22/2016 | RESUBMITTAL | 06/22/2016 | COMPLETED |
| 06/28/2016 | REVISION - - 1ST | 06/29/2016 | COMPLETED |
| 08/11/2016 | REVISION - - 2ND | 08/17/2016 | COMPLETED |
| 10/31/2016 | REVISION - - 3RD | 10/31/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM01945
Permit Status: L of c
Permit Description: NEW SHELL ONLY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/15/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T16CM01945
Permit Description: NEW SHELL ONLY
Total Completed Inspections - 42
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/27/2016 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | |
| 08/22/2016 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | SPOT FOOTINGS OK TO POUR |
| 08/25/2016 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | |
| 08/29/2016 | ELECTRIC - UNDERGROUND | Ingram | Approved | SECONDARY POWER IS APPROVED; PART GIVEN DUE TO SITE LIGHTING IN FUTURE. |
| 09/06/2016 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 09/06/2016 | BUILDING PRE-SLAB | BSTEVENS | Approved | |
| 10/04/2016 | ROOF NAILING | BRUCE_S | Approved | |
| 10/04/2016 | EXT METAL CLIPS/EXT SHEATHING | BRUCE_S | Approved | |
| 10/07/2016 | SITE - SEWER | BRUCE_S | Approved | |
| 10/07/2016 | PLUMBING - YARD WTR LINE/TEST | BRUCE_S | Approved | |
| 10/19/2016 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDUA | Approved | |
| 10/19/2016 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDUA | Approved | |
| 10/26/2016 | FRAMING | BSTEVENS | Approved | |
| 11/03/2016 | SHEET ROCK NAILING | BSTEVENS | Approved | |
| 12/08/2016 | BUILDING ABOVE CEILING | BSTEVENS | Approved | |
| 12/08/2016 | ELECTRIC - ABOVE CEILING | BSTEVENS | Approved | |
| 12/19/2016 | ELECTRIC - SERVICE UPGRADE | BSTEVENS | Approved | |
| 12/20/2016 | TEP CLEARANCE - AM | BSTEVENS | Approved | INCR |
| 12/22/2016 | BUILDING - PROGRESS | BSTEVENS | Approved | OK TO COVER SITE SEWER (COMPLETE) |
| 01/06/2017 | FIRE SPKLR - UG PIPING FLUSH | CBASALDUA | Approved | |
| 01/06/2017 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
| 01/06/2017 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 01/06/2017 | FIRE - FINAL | CBASALDUA | Approved | |
| 02/17/2017 | RIGHT OF WAY - FINAL | DR | Approved | ROW work complete and approved. |
| 02/17/2017 | PLUMBING - BACK WATER VALVE | BSTEVENS | Approved | |
| 02/17/2017 | PLUMBING - ROOF DRAINS | BSTEVENS | Approved | |
| 02/17/2017 | PLUMBING - FINAL | BSTEVENS | Approved | |
| 02/17/2017 | PLUMBING - INTERMEDIATE | BSTEVENS | Approved | |
| 02/17/2017 | BUILDING - FINAL | BSTEVENS | Approved | |
| 02/17/2017 | U VALUE FOR WINDOW | BSTEVENS | Approved | |
| 02/17/2017 | STUCCO MESH | BSTEVENS | Approved | |
| 02/17/2017 | OUTDOOR LIGHTING FINAL | BSTEVENS | Approved | |
| 02/17/2017 | ELECTRIC - FINAL | BSTEVENS | Approved | |
| 02/17/2017 | ELECTRIC - OUTDOOR LIGHTING | BSTEVENS | Approved | |
| 02/17/2017 | ELECTRIC - PROGRESS | BSTEVENS | Approved | |
| 02/17/2017 | ELECTRIC - CONSTRUCTION POWER | BSTEVENS | Approved | |
| 02/17/2017 | ELECTRIC - TEMPORARY SERVICE | BSTEVENS | Approved | |
| 02/17/2017 | ELECTRIC - INTERMEDIATE | BSTEVENS | Approved | |
| 02/22/2017 | NPPO - FINAL | MRUSSO | Approved | |
| 02/22/2017 | SIGN - FINAL | MRUSSO | Approved | |
| 02/22/2017 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 02/22/2017 | ENGINEERING - FINAL | MRUSSO | Approved |