Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T16CM01721
Permit Details
Apply Date:
03/07/2016
Applicant:
HERZOG, STEVEN PAUL
Description:
TI: OFFICE
Architects:
- HERZOG, STEVEN PAUL
Contractors:
- CHESTNUT BUILDING & DESIGN INC
Permit Reviews
Permit Number - T16CM01721
Permit Status: L of c
Permit Description: TI: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/23/2017 | REVISION - - 1ST | 01/27/2017 | COMPLETED |
03/07/2016 | COMMERCIAL - TI | 03/07/2016 | COMPLETED |
03/07/2016 | COMMERCIAL - TI | 04/05/2016 | COMPLETED |
04/05/2016 | RESUBMITTAL - TI ALL | 10/28/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM01721
Permit Status: L of c
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/07/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: L of c
Permit Number: T16CM01721
Permit Description: TI: OFFICE
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/06/2016 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
12/06/2016 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
01/06/2017 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
01/06/2017 | BUILDING ABOVE CEILING | RCAMACHO | Approved | |
01/18/2017 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
01/18/2017 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
01/18/2017 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
01/18/2017 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
01/18/2017 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
01/18/2017 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
01/18/2017 | FIRE - FINAL | CBASALDUA | Approved | |
01/18/2017 | ENGINEERING - FINAL | RLEDONNE | Approved | |
01/26/2017 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | |
01/26/2017 | BUILDING PRE-SLAB | MRAMBER | Approved | |
01/26/2017 | REINFORCED MASONRY PRE-GROUT | MRAMBER | Approved | |
01/26/2017 | SHEET ROCK NAILING | MRAMBER | Approved | |
01/26/2017 | ELECTRIC - PROGRESS | MRAMBER | Approved | |
01/26/2017 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | |
01/26/2017 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | |
01/26/2017 | PLUMBING - PROGRESS | MRAMBER | Approved | |
01/26/2017 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
01/26/2017 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
01/26/2017 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |