Permit: T16CM00478
Permit Details
Apply Date:
01/21/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW METAL BUILDING
Architects:
- CAJERO, NICK FERNANDEZ
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T16CM00478
Permit Status: C of o
Permit Description: NEW METAL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/21/2016 | PLANS OK TO SUBMIT - COMM | 01/22/2016 | COMPLETED |
01/22/2016 | 3RD PARTY REVIEW - COMMERCIAL | 02/23/2016 | COMPLETED |
02/23/2016 | POST 3RD PARTY REVIEW | 03/24/2016 | COMPLETED |
03/24/2016 | POST 3RD PARTY REVIEW | 03/30/2016 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T16CM00478
Permit Status: C of o
Permit Description: NEW METAL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/21/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM00478
Permit Description: NEW METAL BUILDING
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/24/2016 | FIRE SPKLR - UG, PIPING, HYDRO | CBASALDUA | Approved | |
07/06/2016 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
07/06/2016 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
07/06/2016 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
07/18/2016 | PLUMBING - INTERMEDIATE | MPUGH1 | Approved | IVRS - Inspection :* |
09/20/2016 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDUA | Approved | |
09/20/2016 | FIRE - ALARM FINAL | CBASALDUA | Approved | |
09/20/2016 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
09/20/2016 | FIRE SPKLR - UG PIPING FLUSH | CBASALDUA | Approved | |
09/27/2016 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | |
09/27/2016 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
09/27/2016 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
09/27/2016 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
09/27/2016 | PLUMBING - ROUGH, SOIL | MRAMBER | Approved | IVRS - Inspection :* |
09/27/2016 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | IVRS - Inspection :* |
09/27/2016 | SITE - SEWER | MRAMBER | Approved | IVRS - Inspection :* |
09/27/2016 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
09/27/2016 | PLUMBING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
09/28/2016 | FIRE - FINAL | CBASALDUA | Approved | |
09/30/2016 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
09/30/2016 | ELECTRIC - OUTDOOR LIGHTING | MRAMBER | Approved | |
09/30/2016 | ELECTRIC - CABLE DROP | MRAMBER | Approved | |
09/30/2016 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | |
09/30/2016 | RIGHT OF WAY - FINAL | MRAMBER | Approved | |
09/30/2016 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | |
09/30/2016 | ROOF NAILING | MRAMBER | Approved | |
09/30/2016 | BUILDING ABOVE CEILING | MRAMBER | Approved | |
09/30/2016 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
09/30/2016 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
09/30/2016 | OUTDOOR LIGHTING FINAL | MRAMBER | Approved | IVRS - Inspection :* |
09/30/2016 | ELECTRIC - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
09/30/2016 | BUILDING - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
10/03/2016 | NPPO - FINAL | RLEDONNE | Approved | |
10/03/2016 | SIGN - FINAL | RLEDONNE | Approved | |
10/24/2016 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
10/24/2016 | ENGINEERING - FINAL | RLEDONNE | Approved | |
10/27/2016 | PLUMBING - SEWER HCS CONNECT | MRAMBER | Approved |