Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
203 S WILMOT RD
Address NEW:
203 S WILMOT RD
Apply Date:
11/03/2015
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW RESTAURANT
Architects:
  • PHILLIP LAME PRYOR
Contractors:
  • CROSSLANDS CONSTRUCTION CO ,

Permit Reviews

Permit Number - T15CM07660
Permit Status: C of o
Permit Description: NEW RESTAURANT
Start Date Submittal Complete Date Status  
01/14/2016 RESUBMITTAL 01/27/2016 COMPLETED Review Details
01/27/2016 RESUBMITTAL 02/19/2016 COMPLETED Review Details
02/19/2016 REVISION - - 1ST 02/25/2016 COMPLETED Review Details
02/25/2016 REVISION - - 1ST 02/25/2016 COMPLETED Review Details
04/07/2016 REVISION - - 2ND 04/08/2016 COMPLETED Review Details
04/08/2016 REVISION - - 3RD 04/14/2016 COMPLETED Review Details
11/03/2015 PLANS OK TO SUBMIT - COMM 11/03/2015 COMPLETED Review Details
11/03/2015 COMMERCIAL - NEW 12/18/2015 COMPLETED Review Details
12/18/2015 RESUBMITTAL 01/14/2016 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T15CM07660
Permit Status: C of o
Permit Description: NEW RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
11/03/2015 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T15CM07660
Permit Description: NEW RESTAURANT
Total Completed Inspections - 49
Date Description Inspector Results Comments
02/11/2016 ELECTRIC - TEMPORARY SERVICE RMORENO Approved IVRS - Inspection :*
02/11/2016 ELECTRIC - UFER RMORENO Approved IVRS - Inspection :*
02/11/2016 EXCAVATION/LAYOUT REBAR & ZON RMORENO Approved IVRS - Inspection :*
02/26/2016 PLUMBING - ROUGH, SOIL RMORENO Approved IVRS - Inspection :*
03/03/2016 ELECTRIC - UNDERGROUND TVALENC1 Approved IVRS - Inspection :*
03/10/2016 SITE - SEWER RMORENO Approved IVRS - Inspection :*
03/10/2016 PLUMBING - YARD WTR LINE/TEST RMORENO Approved IVRS - Inspection :*
03/10/2016 BUILDING PRE-SLAB RMORENO Approved IVRS - Inspection :*
03/14/2016 FIRE SPKLR - UG, PIPING, HYDRO cclark1 Approved
03/30/2016 REINFORCED MASONRY PRE-GROUT MPUGH1 Approved IVRS - Inspection :*
04/01/2016 FIRE SPKLR - UG PIPING FLUSH C.Clark Approved
04/21/2016 PLUMBING - PROGRESS TVALENC1 Approved IVRS - Inspection :*
04/21/2016 PLUMBING - SEWER HCS CONNECT TVALENC1 Approved IVRS - Inspection :*
04/25/2016 ELECTRIC - OUTDOOR LIGHTING TVALENC1 Approved IVRS - Inspection :*
04/25/2016 ROOF NAILING TVALENC1 Approved IVRS - Inspection :*
04/25/2016 EXT METAL CLIPS/EXT SHEATHING TVALENC1 Approved IVRS - Inspection :*
04/27/2016 PLUMBING - ROOF DRAINS TVALENC1 Approved IVRS - Inspection :*
04/28/2016 FRAMING TVALENC1 Approved IVRS - Inspection :*
04/30/2016 SHEET ROCK NAILING TVALENC1 Approved IVRS - Inspection :*
05/03/2016 NPPO - FINAL MRUSSO Approved
05/12/2016 PLUMBING - GAS PRESSURE TEST TVALENC1 Approved IVRS - Inspection :*
05/31/2016 MECHANICAL - ABOVE CEILING MPUGH1 Approved IVRS - Inspection :*
05/31/2016 PLUMBING - ABOVE CEILING MPUGH1 Approved IVRS - Inspection :*
05/31/2016 ELECTRIC - ABOVE CEILING MPUGH1 Approved IVRS - Inspection :*
05/31/2016 BUILDING ABOVE CEILING MPUGH1 Approved IVRS - Inspection :*
06/03/2016 MECHANICAL - FINAL MPUGH1 Approved IVRS - Inspection :*
06/03/2016 FIRE SPKLR - OH PIPING & HYDRO jvincent Approved see sprink notes under sprink permit
06/06/2016 MECHANICAL - HOODS MPUGH1 Approved IVRS - Inspection :*
06/06/2016 SIGN - FINAL MRUSSO Approved
06/07/2016 FIRE - KITCHEN EXH HOOD FINAL jvincent Approved
06/07/2016 FIRE - ALARM FINAL jvincent Approved
06/07/2016 FIRE SPKLR - FINAL jvincent Approved
06/07/2016 ELECTRIC - FINAL MPUGH1 Approved IVRS - Inspection :*
06/08/2016 MECHANICAL - INTERMEDIATE MPUGH1 Approved IVRS - Inspection :*
06/08/2016 PLUMBING - INTERMEDIATE MPUGH1 Approved IVRS - Inspection :*
06/08/2016 BUILDING - PROGRESS MPUGH1 Approved IVRS - Inspection :*
06/08/2016 U VALUE FOR WINDOW MPUGH1 Approved IVRS - Inspection :*
06/08/2016 STEM WALL/RETAINING WALL MPUGH1 Approved IVRS - Inspection :*
06/08/2016 ELECTRIC - PROGRESS MPUGH1 Approved IVRS - Inspection :*
06/08/2016 ELECTRIC - CONSTRUCTION POWER MPUGH1 Approved IVRS - Inspection :*
06/09/2016 LANDSCAPE - FINAL MRUSSO Approved
06/09/2016 ENGINEERING - FINAL MRUSSO Approved
06/13/2016 BUILDING - FINAL MPUGH1 Approved IVRS - Inspection :* pending fire and eng.
06/13/2016 STUCCO MESH MPUGH1 Approved IVRS - Inspection :*
06/13/2016 OUTDOOR LIGHTING FINAL MPUGH1 Approved IVRS - Inspection :*
06/13/2016 ELECTRIC - INTERMEDIATE MPUGH1 Approved IVRS - Inspection :*
06/13/2016 PLUMBING - FINAL MPUGH1 Approved IVRS - Inspection :*
06/14/2016 FIRE - FINAL jvincent Approved
06/15/2016 HEALTH DEPT - FINAL 724-7908 JKINCAID Approved