Permit: T15CM04368
Permit Details
Apply Date:
06/26/2015
Applicant:
HOBBS, WILLIAM SAMUEL
Description:
TMC WOMEN'S CENTER
Architects:
- HOBBS, WILLIAM SAMUEL
Contractors:
- J E DUNN CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T15CM04368
Permit Status: C of o
Permit Description: TMC WOMEN'S CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/26/2015 | PLANS OK TO SUBMIT - COMM | 06/26/2015 | COMPLETED |
06/26/2015 | COMMERCIAL - TI | 08/13/2015 | COMPLETED |
07/20/2016 | REVISION - - 1ST | 07/20/2016 | COMPLETED |
08/14/2015 | RESUBMITTAL - TI ALL | 09/11/2015 | COMPLETED |
08/30/2016 | REVISION - - 2ND | 08/30/2016 | COMPLETED |
09/11/2015 | RESUBMITTAL | 09/15/2015 | COMPLETED |
09/15/2015 | RESUBMITTAL | 09/15/2015 | COMPLETED |
09/15/2015 | RESUBMITTAL | 09/23/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T15CM04368
Permit Status: C of o
Permit Description: TMC WOMEN'S CENTER
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/26/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM04368
Permit Description: TMC WOMEN'S CENTER
Total Completed Inspections - 48
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/02/2015 | PLUMBING - ROUGH, SOIL | BBENEDOI | Approved | 11373, 11372 TRS OK |
11/13/2015 | PLUMBING - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
11/20/2015 | PLUMBING - ABOVE CEILING | BBENEDOI | Approved | REMAINDER OF DOMESTIC WATER PIPING TESTED AND OK TO INSULATE. PROVIDE A MIN. 100 PSI HYDROSTATIC TEST ON HYDRONIC PIPING. |
11/20/2015 | ELECTRIC - UFER | BBENEDOI | Approved | IVRS - Inspection :* |
11/20/2015 | FRAMING | BBENEDOI | Approved | IVRS - Inspection :* |
11/24/2015 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDOI | Approved | TRANSFORMER PAD STEM WALLS |
12/01/2015 | ELECTRIC - SERVICE UPGRADE | BBENEDOI | Approved | IVRS - Inspection :* |
12/02/2015 | TEP CLEARANCE - AM | bbenedon | Approved | recn |
12/18/2015 | BUILDING - FINAL | bbenedo | Approved | Tr's and waiting 11373, 11372, ok to use. Label piping abv access panels. |
12/18/2015 | ELECTRIC - ABOVE CEILING | bbenedo | Approved | |
12/18/2015 | MECHANICAL - ABOVE CEILING | bbenedo | Approved | |
12/22/2015 | FIRE SPKLR - FINAL | nsprenger | Approved | sprinkler company did not call in their final |
09/29/2016 | STUCCO MESH | JMILITEL | Approved | STUCCO MESH OK TO COVER. |
10/05/2016 | BUILDING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
10/05/2016 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENC1 | Approved | IVRS - Inspection :* |
10/19/2016 | MECHANICAL - HYDRONIC PIPING | TVALENC1 | Approved | IVRS - Inspection :* |
11/03/2016 | BUILDING ABOVE CEILING | TVALENC1 | Approved | IVRS - Inspection :* |
11/14/2016 | OUTDOOR LIGHTING FINAL | TVALENC1 | Approved | IVRS - Inspection :* 1- HAD A PRE CON MEETING WITH THE G.C. ON TEMP C OF O REQUIREMENTS. |
11/17/2016 | PLUMBING - GAS PRESSURE TEST | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | PLUMBING - MEDICAL GAS/TEST | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | PLUMBING - MD GAS/PRECONST MTG | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | ELECTRIC - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | ELECTRIC - TEMP POWER FOR TEST | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | ELECTRIC - CONSTRUCTION POWER | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | ELECTRIC - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | ELECTRIC - TEMPORARY SERVICE | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | ELECTRIC - UNDERGROUND | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | PLUMBING - PROGRESS | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | MECHANICAL - INTERMEDIATE | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | SHEET ROCK NAILING | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | U VALUE FOR WINDOW | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | REINFORCED MASONRY PRE-GROUT | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | BUILDING PRE-SLAB | TVALENC1 | Approved | IVRS - Inspection :* |
11/17/2016 | STEM WALL/RETAINING WALL | TVALENC1 | Approved | IVRS - Inspection :* |
11/22/2016 | MECHANICAL - FINAL | TVALENC1 | Approved | |
11/22/2016 | PLUMBING - FINAL | TVALENC1 | Approved | |
11/22/2016 | PLUMBING - MEDICAL GAS/FINAL | TVALENC1 | Approved | |
11/22/2016 | ELECTRIC - OUTDOOR LIGHTING | TVALENC1 | Approved | |
11/22/2016 | ELECTRIC - FINAL | TVALENC1 | Approved | |
12/02/2016 | ENGINEERING - FINAL | DROBERTS | Approved | OK FOR THE TEMPORARY CERTIFICATE OF OCCUPANCY FOR STOCKING ONLY |
12/02/2016 | LANDSCAPE - FINAL | DROBERTS | Approved | OK FOR THE TEMPORARY CERTIFICATE OF OCCUPANCY FOR STOCKING ONLY |
12/02/2016 | SIGN - FINAL | DROBERTS | Approved | OK FOR THE TEMPORARY CERTIFICATE OF OCCUPANCY FOR STOCKING ONLY |
12/02/2016 | NPPO - FINAL | DROBERTS | Approved | OK FOR THE TEMPORARY CERTIFICATE OF OCCUPANCY FOR STOCKING ONLY |
12/02/2016 | RIGHT OF WAY - FINAL | DRussell | Approved | |
12/02/2016 | FIRE - FINAL | jvincent | Approved | labeling smoke dampers labeling inspectors test valve access door |
12/02/2016 | FIRE - ALARM FINAL | jvincent | Approved | |
12/05/2016 | ROOF NAILING | TVALENCIA | Approved | |
01/20/2017 | PERMIT FINALED | DROBERTS | Approved |