Apply Date:
04/06/2015
Applicant:
CDG ARCHITECTS
Description:
OFFICES
Architects:
- CDG ARCHITECTS
Contractors:
- B F L CONSTRUCTION CO INC ,
Permit Reviews
Permit Number - T15CM02238
Permit Status: C of o
Permit Description: OFFICES
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/06/2015 | PLANS OK TO SUBMIT - COMM | 04/07/2015 | COMPLETED |
04/07/2015 | COMMERCIAL - TI | 05/04/2015 | COMPLETED |
06/08/2015 | RESUBMITTAL | 07/08/2015 | COMPLETED |
07/08/2015 | COMMERCIAL - TI | 07/09/2015 | COMPLETED |
10/19/2015 | REVISION - - 1ST | 10/22/2015 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T15CM02238
Permit Status: C of o
Permit Description: OFFICES
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/06/2015 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T15CM02238
Permit Description: OFFICES
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/07/2015 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | FOOTER AT RAMP |
08/17/2015 | PLUMBING - ROUGH, SOIL | TVALENCIA | Approved | 1. DWV WATER TEST PROVIDED 2. P.O.C. OF NEW BLDG DRAIN OK 3. SHALL RED LINE DRAWING SHOWING LOCATION OF WASTE 4. THIS INSPECTION IS FOR TOILET ROOM #244 5. OK TO BACK FILL TRENCH |
08/19/2015 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
10/07/2015 | PLUMBING - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
11/13/2015 | PLUMBING - GAS PRESSURE TEST | AQUIROZ | Approved | IVRS - Inspection :* |
11/23/2015 | PLUMBING - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/23/2015 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
11/23/2015 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/23/2015 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
11/30/2015 | MECHANICAL - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
11/30/2015 | MECHANICAL - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
12/16/2015 | ELECTRIC - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
12/16/2015 | ELECTRIC - ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
12/21/2015 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
12/23/2015 | NPPO - FINAL | MRUSSO | Approved | |
12/23/2015 | SIGN - FINAL | MRUSSO | Approved | |
12/23/2015 | LANDSCAPE - FINAL | MRUSSO | Approved | |
12/23/2015 | ENGINEERING - FINAL | MRUSSO | Approved | WALKED THE SITE WITH THE SUPERINTENDENT, ENSURE CONSTRUCTION IS COMPLETED PER THE APPROVED PLAN PRIOR TO FINAL APPROVAL |
01/04/2016 | FIRE SPKLR - FINAL | nspreng1 | Approved | |
01/05/2016 | FIRE - ALARM FINAL | nsprenger | Approved | |
01/05/2016 | RIGHT OF WAY - FINAL | DROBERTSON | Approved | |
01/06/2016 | FIRE - FINAL | nsprenger | Approved | |
01/08/2016 | MECHANICAL - FINAL | AQUIROZ | Approved | APPROVED PER INSP SHEET |
01/08/2016 | ELECTRIC - FINAL | AQUIROZ | Approved | APPROVED PER INSP SHEET |
01/08/2016 | PLUMBING - PROGRESS | AQUIROZ | Approved | APPROVED PER INSP SHEET |
01/08/2016 | MECHANICAL - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
01/08/2016 | PLUMBING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
01/08/2016 | ELECTRIC - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |