Permit Details

Status:
C of o
Type:
COMMERCIAL ALTERATION
Apply Date:
03/27/2015
Applicant:
COLBY MOELLER
Description:
RESTAURANT
Contractors:
  • LLOYD CONSTRUCTION COMPANY INC ,

Permit Reviews

Permit Number - T15CM02052
Permit Status: C of o
Permit Description: RESTAURANT
Start Date Submittal Complete Date Status  
03/27/2015 PLANS OK TO SUBMIT - COMM 03/31/2015 COMPLETED Review Details
03/31/2015 COMMERCIAL - TI 04/21/2015 COMPLETED Review Details
04/24/2015 RESUBMITTAL 05/06/2015 COMPLETED Review Details
05/06/2015 WALK THRU - COMM 05/06/2015 COMPLETED Review Details
05/06/2015 OTHER 07/02/2015 COMPLETED Review Details
07/02/2015 REVISION - - 1ST 07/02/2015 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T15CM02052
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
03/27/2015 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T15CM02052
Permit Description: RESTAURANT
Total Completed Inspections - 34
Date Description Inspector Results Comments
05/11/2015 ELECTRIC - UNDERGROUND BSTEVENS Approved
05/11/2015 PLUMBING - ROUGH, SOIL BSTEVENS Approved
05/20/2015 ELECTRIC - INTERMEDIATE BSTEVENS Approved
05/21/2015 FRAMING BSTEVENS Approved
05/21/2015 PLUMBING - INTERMEDIATE BSTEVENS Approved
05/27/2015 SHEET ROCK NAILING BSTEVENS Approved
06/19/2015 PLUMBING - ABOVE CEILING BSTEVENS Approved
06/19/2015 MECHANICAL - ABOVE CEILING BSTEVENS Approved
06/19/2015 BUILDING ABOVE CEILING BSTEVENS Approved
06/25/2015 TEP CLEARANCE - AM dquinn Approved clear recon
06/25/2015 GAS CLEARANCE dquinn Approved gas clear
06/26/2015 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
06/26/2015 ELECTRIC - PROGRESS JMILITEL Approved IVRS - Inspection :*
06/26/2015 ELECTRIC - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
06/26/2015 PLUMBING - GAS PRESSURE TEST DQUINN Approved
06/30/2015 U VALUE FOR WINDOW JMILITEL Approved IVRS - Inspection :*
07/01/2015 MECHANICAL - HOODS JMILITEL Approved IVRS - Inspection :*
07/01/2015 SITE - SEWER JMILITEL Approved IVRS - Inspection :*
07/01/2015 PLUMBING - PROGRESS JMILITEL Approved IVRS - Inspection :*
07/01/2015 BUILDING - PROGRESS JMILITEL Approved IVRS - Inspection :*
07/02/2015 FIRE SPKLR - FINAL CSCHULTZ Approved
07/02/2015 FIRE - ALARM FINAL CSCHULTZ Approved
07/02/2015 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
07/02/2015 PLUMBING - FINAL JMILITEL Approved IVRS - Inspection :*
07/02/2015 ELECTRIC - FINAL JMILITEL Approved IVRS - Inspection :*
07/06/2015 NPPO - FINAL MRUSSO Approved
07/06/2015 SIGN - FINAL MRUSSO Approved
07/06/2015 LANDSCAPE - FINAL MRUSSO Approved
07/06/2015 ENGINEERING - FINAL MRUSSO Approved
07/08/2015 RIGHT OF WAY - FINAL CMCNELLIS Approved
07/09/2015 HEALTH DEPT - FINAL 724-7908 ELOPEZ Approved PER SONYA
07/14/2015 FIRE - FINAL CBASALDUA Approved
07/22/2015 BUILDING - FINAL JMILITEL Approved OK TO APPLY FOR C OF O
07/22/2015 STUCCO MESH JMILITEL Approved