Permit: T14CM07359
Permit Details
Apply Date:
10/30/2014
Applicant:
WEINER, PAUL ALAN
Description:
ADDITION OF NEW OFFICE/GIFT SHOP FOR BOTANICAL GARDENS;
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T14CM07359
Permit Status: C of o
Permit Description: ADDITION OF NEW OFFICE/GIFT SHOP FOR BOTANICAL GARDENS;
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/13/2015 | RESUBMITTAL | 02/20/2015 | COMPLETED |
02/20/2015 | RESUBMITTAL | 04/24/2015 | COMPLETED |
04/24/2015 | REVISION - - 1ST | 04/24/2015 | COMPLETED |
04/24/2015 | REVISION - - 1ST | 05/07/2015 | COMPLETED |
10/30/2014 | PLANS OK TO SUBMIT - COMM | 10/30/2014 | COMPLETED |
10/30/2014 | COMMERCIAL - TI | 12/03/2014 | COMPLETED |
12/29/2014 | RESUBMITTAL - TI ALL | 02/03/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM07359
Permit Status: C of o
Permit Description: ADDITION OF NEW OFFICE/GIFT SHOP FOR BOTANICAL GARDENS;
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/30/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM07359
Permit Description: ADDITION OF NEW OFFICE/GIFT SHOP FOR BOTANICAL GARDENS;
Total Completed Inspections - 45
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/24/2015 | PLUMBING - YARD WTR LINE/TEST | JMILITELLO | Approved | OK TO BACKFILL YARD WATERLINE |
03/24/2015 | PLUMBING - YARD WTR LINE/TEST | JMILITEL | Approved | IVRS - Inspection :* |
04/02/2015 | ELECTRIC - CONSTRUCTION POWER | JMILITEL | Approved | IVRS - Inspection :* |
04/03/2015 | SITE - SEWER | JMILITELLO | Approved | OK TO BACKFILL SITE SEWER |
04/03/2015 | SITE - SEWER | JMILITEL | Approved | IVRS - Inspection :* |
04/20/2015 | PLUMBING - ROUGH, SOIL | JMILITEL | Approved | IVRS - Inspection :* |
04/28/2015 | ELECTRIC - UFER | JMILITEL | Approved | IVRS - Inspection :* |
04/28/2015 | BUILDING PRE-SLAB | JMILITEL | Approved | IVRS - Inspection :* |
05/04/2015 | EXCAVATION/LAYOUT REBAR & ZON | JMILITELLO | Approved | OK TO POUR FOOTINGS |
05/04/2015 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
06/02/2015 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/02/2015 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
06/10/2015 | ROOF NAILING | BBENEDOI | Approved | IVRS - Inspection :* |
06/12/2015 | STEM WALL/RETAINING WALL | JMILITEL | Approved | IVRS - Inspection :* |
06/12/2015 | FRAMING | JMILITEL | Approved | IVRS - Inspection :* |
06/12/2015 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/12/2015 | PLUMBING - ROOF DRAINS | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | BUILDING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | REINFORCED MASONRY PRE-GROUT | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
06/17/2015 | ELECTRIC - UNDERGROUND | JMILITEL | Approved | IVRS - Inspection :* |
06/19/2015 | EXT METAL CLIPS/EXT SHEATHING | JMILITEL | Approved | IVRS - Inspection :* |
06/26/2015 | U VALUE FOR WINDOW | MPUGH | Approved | IVRS - Inspection :* |
07/08/2015 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
07/08/2015 | STUCCO MESH | JMILITEL | Approved | IVRS - Inspection :* |
07/22/2015 | ELECTRIC - CABLE DROP | JMILITEL | Approved | IVRS - Inspection :* |
07/23/2015 | TEP CLEARANCE - AM | JMILITELLO | Approved | ECO |
08/06/2015 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
09/01/2015 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
09/01/2015 | PLUMBING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
09/01/2015 | OUTDOOR LIGHTING FINAL | JMILITEL | Approved | IVRS - Inspection :* |
09/01/2015 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
09/04/2015 | RIGHT OF WAY - FINAL | JCAZ | Approved | |
09/04/2015 | NPPO - FINAL | RLEDONNE | Approved | |
09/04/2015 | SIGN - FINAL | RLEDONNE | Approved | |
09/08/2015 | MECHANICAL - FINAL | BSTEVENS | Approved | |
09/08/2015 | FIRE - ALARM FINAL | CCLARK | Approved | TAMPER TESTED AND APPROVED. |
09/08/2015 | FIRE - FINAL | CCLARK | Approved | |
09/10/2015 | BUILDING - FINAL | BSTEVENS | Approved | FIRE APPROVED ON 09/08/15 |
09/28/2015 | LANDSCAPE - FINAL | DROBERTS | Approved | |
09/28/2015 | ENGINEERING - FINAL | DROBERTS | Approved |