Permit Details

Status:
L of c
Type:
COMMERCIAL ALTERATION
Address:
7250 S TUCSON BL
Apply Date:
10/23/2014
Applicant:
SANDRA KUKLA
Description:
T.I AND EXTERIOR GLAZING AND PARKING- TAA
Contractors:
  • HENSEL PHELPS CONSTRUCTION CO ,

Permit Reviews

Permit Number - T14CM07159
Permit Status: L of c
Permit Description: T.I AND EXTERIOR GLAZING AND PARKING- TAA
Start Date Submittal Complete Date Status  
01/05/2015 RESUBMITTAL 01/05/2015 COMPLETED Review Details
01/05/2015 RESUBMITTAL 03/11/2015 COMPLETED Review Details
03/17/2015 REVISION - - 1ST 03/17/2015 COMPLETED Review Details
07/02/2015 REVISION - - 1ST 11/17/2015 COMPLETED Review Details
10/23/2014 PLANS OK TO SUBMIT - COMM 10/23/2014 COMPLETED Review Details
10/23/2014 COMMERCIAL - TI 12/11/2014 COMPLETED Review Details
11/17/2015 REVISION - - 2ND 11/17/2015 COMPLETED Review Details
12/11/2014 RESUBMITTAL 01/05/2015 COMPLETED Review Details

Completed Inspections

Permit Status: L of c
Permit Number: T14CM07159
Permit Description: T.I AND EXTERIOR GLAZING AND PARKING- TAA
Total Completed Inspections - 33
Date Description Inspector Results Comments
05/27/2015 PLUMBING - ROOF DRAINS MRAMBER Approved DUE TO EXISTING CONDITIONS, ALL ROOF DRAINS COULD NOT BE TESTED. ALL PIPING IS PROPERLY SUPPORTED. CONTRACTOR ASSUMES RESPONSIBILITY FOR ANY LEAKS WHICH MAY OCCUR
05/27/2015 PLUMBING - ROOF DRAINS MRAMBER Approved IVRS - Inspection :*
06/22/2015 PLUMBING - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
08/04/2015 EXCAVATION/LAYOUT REBAR & ZON MRAMBER Approved IVRS - Inspection :*
08/27/2015 ELECTRIC - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
09/11/2015 MECHANICAL - INTERMEDIATE MRAMBER Approved IVRS - Inspection :*
09/11/2015 MECHANICAL - HYDRONIC PIPING MRAMBER Approved IVRS - Inspection :*
09/11/2015 PLUMBING - PROGRESS MRAMBER Approved IVRS - Inspection :*
09/11/2015 PLUMBING - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
09/11/2015 BUILDING - PROGRESS MRAMBER Approved IVRS - Inspection :*
09/15/2015 MECHANICAL - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
09/15/2015 ELECTRIC - ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
09/15/2015 FIREWALL/FIREBARRIER/FIRESTOP MRAMBER Approved IVRS - Inspection :*
09/15/2015 BUILDING ABOVE CEILING MRAMBER Approved IVRS - Inspection :*
09/29/2015 SHEET ROCK NAILING MPUGH1 Approved IVRS - Inspection :*
09/29/2015 U VALUE FOR WINDOW MPUGH1 Approved IVRS - Inspection :*
09/29/2015 STUCCO MESH MPUGH1 Approved IVRS - Inspection :*
09/29/2015 FRAMING MPUGH1 Approved IVRS - Inspection :*
09/29/2015 EXT METAL CLIPS/EXT SHEATHING MPUGH1 Approved IVRS - Inspection :*
09/29/2015 REINFORCED MASONRY PRE-GROUT MPUGH1 Approved IVRS - Inspection :*
09/29/2015 BUILDING PRE-SLAB MPUGH1 Approved IVRS - Inspection :*
09/29/2015 STEM WALL/RETAINING WALL MPUGH1 Approved IVRS - Inspection :*
09/29/2015 ELECTRIC - PROGRESS MPUGH1 Approved IVRS - Inspection :*
09/29/2015 ELECTRIC - CONSTRUCTION POWER MPUGH1 Approved IVRS - Inspection :*
10/02/2015 FIRE - ALARM FINAL CBASALDUA Approved
10/02/2015 FIRE SPKLR - FINAL CBASALDUA Approved
10/02/2015 FIRE - FINAL CBASALDUA Approved
10/02/2015 MECHANICAL - FINAL MPUGH1 Approved IVRS - Inspection :*
10/02/2015 PLUMBING - FINAL MPUGH1 Approved IVRS - Inspection :*
10/05/2015 SIGN - FINAL RLEDONNE Approved
10/05/2015 ENGINEERING - FINAL RLEDONNE Approved
10/06/2015 BUILDING - FINAL MRAMBER Approved CHANGED FROM AP TO PA TO ALLOW FOR REINSPECTION PER R2
10/06/2015 ELECTRIC - FINAL MRAMBER Approved IVRS - Inspection :*

Documents

File Name Document Type  
None LETTER OF COMPLETION VIEW
None DOCUMENTS VIEW