Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Withdrwn
Type:
COMMERCIAL ALTERATION
Apply Date:
10/17/2014
Applicant:
N/A
Description:
TI: SOUTHGATE ACADEMY
Architects:
  • NAKHAI, FARZAD
Contractors:
  • 4 DIAMOND BUILDERS

Permit Reviews

Permit Number - T14CM07018
Permit Status: Withdrwn
Permit Description: TI: SOUTHGATE ACADEMY
Start Date Submittal Complete Date Status  
01/18/2017 REVISION - - 2ND 01/18/2017 COMPLETED Review Details
07/18/2017 REVISION - - 3RD 07/18/2017 COMPLETED Review Details
07/25/2017 REVISION - - 3RD 08/02/2017 COMPLETED Review Details
08/04/2017 REVISION - - 3RD 08/09/2017 COMPLETED Review Details
08/15/2017 REVISION - - 3RD 08/15/2017 COMPLETED Review Details
09/03/2015 RESUBMITTAL 09/22/2015 COMPLETED Review Details
09/22/2015 RESUBMITTAL 11/21/2016 COMPLETED Review Details
10/17/2014 PLANS OK TO SUBMIT - COMM 10/17/2014 COMPLETED Review Details
10/17/2014 COMMERCIAL - TI 11/13/2014 COMPLETED Review Details
11/21/2016 REVISION - - 1ST 12/27/2016 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T14CM07018
Permit Status: Withdrwn
Permit Description: TI: SOUTHGATE ACADEMY
Total Outstanding Activity Conditions - 11
Date Name
10/17/2014 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
10/27/2014 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
10/27/2014 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/27/2014 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
10/27/2014 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
10/27/2014 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
10/27/2014 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
10/27/2014 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
10/27/2014 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
10/27/2014 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
10/27/2014 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.

Outstanding Inspections

Permit Status: Withdrwn
Permit Number: T14CM07018
Permite Description: TI: SOUTHGATE ACADEMY
Total Outstanding Inspections - 24
Last Inspection Date Description Inspector Results Comments
STEM WALL/RETAINING WALL N/A Not Inspected
BUILDING PRE-SLAB N/A Not Inspected
REINFORCED MASONRY PRE-GROUT N/A Not Inspected
ROOF NAILING N/A Not Inspected
BUILDING ABOVE CEILING N/A Not Inspected
U VALUE FOR WINDOW N/A Not Inspected
BUILDING - PROGRESS N/A Not Inspected
ELECTRIC - ABOVE CEILING N/A Not Inspected
ELECTRIC - PROGRESS N/A Not Inspected
ELECTRIC - OUTDOOR LIGHTING N/A Not Inspected
PLUMBING - INTERMEDIATE N/A Not Inspected
PLUMBING - ROOF DRAINS N/A Not Inspected
PLUMBING - GAS PRESSURE TEST N/A Not Inspected
SITE - SEWER N/A Not Inspected
MECHANICAL - ABOVE CEILING N/A Not Inspected
03/15/2018 BUILDING - FINAL N/A Not ready for Inspection CLEAR UP ALL OPEN INSPECTIONS PRIOR TO FINALS
CANCELED
04/06/2017 EXT METAL CLIPS/EXT SHEATHING N/A Partial Approval EAST AND WEST COURT YARD WALLS ONLY
05/03/2017 FIREWALL/FIREBARRIER/FIRESTOP N/A Partial Approval west firewall ok to mud and tape
05/03/2017 ELECTRIC - INTERMEDIATE N/A Partial Approval gym ok
06/05/2017 STUCCO MESH N/A Partial Approval west court yard ok
06/08/2017 FRAMING N/A Not ready for Inspection
06/08/2017 PLUMBING - ABOVE CEILING N/A Not ready for Inspection
06/08/2017 PLUMBING - PROGRESS N/A Not ready for Inspection
09/20/2016 PLUMBING - ROUGH, SOIL N/A Partial Approval IVRS - Inspection :*COURT YARD #2 ON THE EAST SIDE

Completed Inspections

Permit Status: Withdrwn
Permit Number: T14CM07018
Permit Description: TI: SOUTHGATE ACADEMY
Total Completed Inspections - 7
Date Description Inspector Results Comments
10/26/2016 EXCAVATION/LAYOUT REBAR & ZON ESTEVEN1 Approved IVRS - Inspection :*
11/09/2017 SHEET ROCK NAILING RCAMACHO Approved
03/13/2018 NPPO - FINAL RLEDONNE Approved
03/13/2018 SIGN - FINAL RLEDONNE Approved
03/13/2018 LANDSCAPE - FINAL RLEDONNE Approved
03/13/2018 ENGINEERING - FINAL RLEDONNE Approved
03/14/2018 RIGHT OF WAY - FINAL cfarren Approved CFO no sign of work being done in ROW - close

Documents

File Name Document Type  
001_COVER.TIF CONSTRPLANS VIEW
002_A-1.TIF CONSTRPLANS VIEW
003_A-2.TIF CONSTRPLANS VIEW
004_A-3.TIF CONSTRPLANS VIEW
005_A-3A.TIF CONSTRPLANS VIEW
006_A-4.TIF CONSTRPLANS VIEW
007_A-5.TIF CONSTRPLANS VIEW
008_A-6.TIF CONSTRPLANS VIEW
009_A-6A.TIF CONSTRPLANS VIEW
010_A-7.TIF CONSTRPLANS VIEW
011_A-8.TIF CONSTRPLANS VIEW
012_A-9.TIF CONSTRPLANS VIEW
013_A-9A.TIF CONSTRPLANS VIEW
014_A-10.TIF CONSTRPLANS VIEW
014_A-10A.TIF CONSTRPLANS VIEW
015_A-11.TIF CONSTRPLANS VIEW
016_TS-1.TIF CONSTRPLANS VIEW
017_TS-2.TIF CONSTRPLANS VIEW
018_TS-3.TIF CONSTRPLANS VIEW
019_AV-1.TIF CONSTRPLANS VIEW
020_AV-2.TIF CONSTRPLANS VIEW
016_S1.0.TIF CONSTRPLANS VIEW
021_S.1.TIF CONSTRPLANS VIEW
022_S.2.TIF CONSTRPLANS VIEW
023_S.3.TIF CONSTRPLANS VIEW
024_S.4.TIF CONSTRPLANS VIEW
025_S.5.TIF CONSTRPLANS VIEW
026_S.6.TIF CONSTRPLANS VIEW
027_S.7.TIF CONSTRPLANS VIEW
028_S.8.TIF CONSTRPLANS VIEW
029_E-1.1.TIF CONSTRPLANS VIEW
030_E-1.2.TIF CONSTRPLANS VIEW
031_E-2.1.TIF CONSTRPLANS VIEW
032_E-2.2.TIF CONSTRPLANS VIEW
033_E-3.1.TIF CONSTRPLANS VIEW
034_E-4.1.TIF CONSTRPLANS VIEW
035_E-4.2.TIF CONSTRPLANS VIEW
036_E-4.3.TIF CONSTRPLANS VIEW
037_E-5.1.TIF CONSTRPLANS VIEW
038_E-5.2.TIF CONSTRPLANS VIEW
039_DM1.1.TIF CONSTRPLANS VIEW
040_M1.1.TIF CONSTRPLANS VIEW
041_M1.2.TIF CONSTRPLANS VIEW
042_M1.3.TIF CONSTRPLANS VIEW
043_M3.1.TIF CONSTRPLANS VIEW
044_M6.1.TIF CONSTRPLANS VIEW
045_M6.2.TIF CONSTRPLANS VIEW
046_M8.1.TIF CONSTRPLANS VIEW
047_M9.1.TIF CONSTRPLANS VIEW
048_M9.2.TIF CONSTRPLANS VIEW
None DOCUMENTS VIEW