Permit: T14CM07018
Permit Details
Apply Date:
10/17/2014
Applicant:
N/A
Description:
TI: SOUTHGATE ACADEMY
Architects:
- NAKHAI, FARZAD
Contractors:
- 4 DIAMOND BUILDERS
Permit Reviews
Permit Number - T14CM07018
Permit Status: Withdrwn
Permit Description: TI: SOUTHGATE ACADEMY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/18/2017 | REVISION - - 2ND | 01/18/2017 | COMPLETED |
07/18/2017 | REVISION - - 3RD | 07/18/2017 | COMPLETED |
07/25/2017 | REVISION - - 3RD | 08/02/2017 | COMPLETED |
08/04/2017 | REVISION - - 3RD | 08/09/2017 | COMPLETED |
08/15/2017 | REVISION - - 3RD | 08/15/2017 | COMPLETED |
09/03/2015 | RESUBMITTAL | 09/22/2015 | COMPLETED |
09/22/2015 | RESUBMITTAL | 11/21/2016 | COMPLETED |
10/17/2014 | PLANS OK TO SUBMIT - COMM | 10/17/2014 | COMPLETED |
10/17/2014 | COMMERCIAL - TI | 11/13/2014 | COMPLETED |
11/21/2016 | REVISION - - 1ST | 12/27/2016 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM07018
Permit Status: Withdrwn
Permit Description: TI: SOUTHGATE ACADEMY
Total Outstanding Activity Conditions - 11
Date | Name |
---|---|
10/17/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
10/27/2014 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. |
10/27/2014 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
10/27/2014 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
10/27/2014 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
10/27/2014 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
10/27/2014 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
10/27/2014 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
10/27/2014 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
10/27/2014 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
10/27/2014 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Withdrwn
Permit Number: T14CM07018
Permite Description: TI: SOUTHGATE ACADEMY
Total Outstanding Inspections - 24
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
STEM WALL/RETAINING WALL | N/A | Not Inspected | ||
BUILDING PRE-SLAB | N/A | Not Inspected | ||
REINFORCED MASONRY PRE-GROUT | N/A | Not Inspected | ||
ROOF NAILING | N/A | Not Inspected | ||
BUILDING ABOVE CEILING | N/A | Not Inspected | ||
U VALUE FOR WINDOW | N/A | Not Inspected | ||
BUILDING - PROGRESS | N/A | Not Inspected | ||
ELECTRIC - ABOVE CEILING | N/A | Not Inspected | ||
ELECTRIC - PROGRESS | N/A | Not Inspected | ||
ELECTRIC - OUTDOOR LIGHTING | N/A | Not Inspected | ||
PLUMBING - INTERMEDIATE | N/A | Not Inspected | ||
PLUMBING - ROOF DRAINS | N/A | Not Inspected | ||
PLUMBING - GAS PRESSURE TEST | N/A | Not Inspected | ||
SITE - SEWER | N/A | Not Inspected | ||
MECHANICAL - ABOVE CEILING | N/A | Not Inspected | ||
03/15/2018 | BUILDING - FINAL | N/A | Not ready for Inspection | CLEAR UP ALL OPEN INSPECTIONS PRIOR TO FINALS CANCELED |
04/06/2017 | EXT METAL CLIPS/EXT SHEATHING | N/A | Partial Approval | EAST AND WEST COURT YARD WALLS ONLY |
05/03/2017 | FIREWALL/FIREBARRIER/FIRESTOP | N/A | Partial Approval | west firewall ok to mud and tape |
05/03/2017 | ELECTRIC - INTERMEDIATE | N/A | Partial Approval | gym ok |
06/05/2017 | STUCCO MESH | N/A | Partial Approval | west court yard ok |
06/08/2017 | FRAMING | N/A | Not ready for Inspection | |
06/08/2017 | PLUMBING - ABOVE CEILING | N/A | Not ready for Inspection | |
06/08/2017 | PLUMBING - PROGRESS | N/A | Not ready for Inspection | |
09/20/2016 | PLUMBING - ROUGH, SOIL | N/A | Partial Approval | IVRS - Inspection :*COURT YARD #2 ON THE EAST SIDE |
Completed Inspections
Permit Status: Withdrwn
Permit Number: T14CM07018
Permit Description: TI: SOUTHGATE ACADEMY
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2016 | EXCAVATION/LAYOUT REBAR & ZON | ESTEVEN1 | Approved | IVRS - Inspection :* |
11/09/2017 | SHEET ROCK NAILING | RCAMACHO | Approved | |
03/13/2018 | NPPO - FINAL | RLEDONNE | Approved | |
03/13/2018 | SIGN - FINAL | RLEDONNE | Approved | |
03/13/2018 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
03/13/2018 | ENGINEERING - FINAL | RLEDONNE | Approved | |
03/14/2018 | RIGHT OF WAY - FINAL | cfarren | Approved | CFO no sign of work being done in ROW - close |