Permit Reviews
Permit Number - T14CM05234
Permit Status: C of o
Permit Description: SFR MODELA0001 T14-M0030
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/13/2014 | RESIDENTIAL - BLDG-MODEL PLAN/ENGINE/WALK THRU | 08/13/2014 | COMPLETED |
| 12/04/2014 | REVISION - WALK THRU | 12/04/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM05234
Permit Status: C of o
Permit Description: SFR MODELA0001 T14-M0030
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/13/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM05234
Permit Description: SFR MODELA0001 T14-M0030
Total Completed Inspections - 25
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/09/2014 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | YARD LINE TEST DOWN. CORRECT LEAK |
| 12/09/2014 | PLUMBING - YARD WTR LINE/TEST | BBENEDOI | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 12/09/2014 | ELECTRIC - UFER | BBENEDOI | Approved | IVRS - Inspection :* |
| 12/09/2014 | BUILDING PRE-SLAB | BBENEDOI | Approved | IVRS - Inspection :* |
| 12/09/2014 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDOI | Approved | IVRS - Inspection :* |
| 12/09/2014 | PLUMBING - SEWER HCS CONNECT | BBENEDOI | Approved | IVRS - Inspection :* |
| 12/24/2014 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 12/24/2014 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 02/24/2015 | ELECTRIC - TEMPORARY SERVICE | BBENEDOI | Approved | IVRS - Inspection :* |
| 02/24/2015 | ELECTRIC - TEMP POWER FOR TEST | BBENEDOI | Approved | IVRS - Inspection :* |
| 02/24/2015 | STUCCO MESH | BBENEDOI | Approved | IVRS - Inspection :* |
| 03/02/2015 | FRAMING | BBENEDOI | Approved | IVRS - Inspection :* |
| 03/02/2015 | MECHANICAL - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
| 03/06/2015 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | |
| 03/10/2015 | SHEET ROCK NAILING | DQUINN | Approved | |
| 05/08/2015 | BUILDING - FINAL | DQUINN | Approved | PER DQUINN OVER THE PHONE |
| 05/08/2015 | BUILDING - FINAL | DQUINN | Approved | NEED INSULATION CERT ONLY FOR FINAL. ALL ELSE OK |
| 05/08/2015 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | |
| 05/08/2015 | ELECTRIC - FINAL | DQUINN | Approved | |
| 05/08/2015 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | |
| 05/08/2015 | PLUMBING - INTERMEDIATE | DQUINN | Approved | |
| 05/08/2015 | PLUMBING - FINAL | DQUINN | Approved | |
| 05/08/2015 | PLUMBING - GAS PRESS TEST FNL | DQUINN | Approved | |
| 05/08/2015 | MECHANICAL - FINAL | DQUINN | Approved | |
| 05/08/2015 | U VALUE FOR WINDOW | DQUINN | Approved |