Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T14CM03839
Permit Details
Apply Date:
06/20/2014
Applicant:
AMBER WILLIAMS
Description:
PALO VERDE BEHAVIORAL HEALTH BUILDING
Architects:
- MOBLEY, JAMES WYNNE
Contractors:
- WESPAC CONSTRUCTION INC ,
Permit Reviews
Permit Number - T14CM03839
Permit Status: C of o
Permit Description: PALO VERDE BEHAVIORAL HEALTH BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/20/2014 | PLANS OK TO SUBMIT - COMM | 06/20/2014 | COMPLETED |
06/20/2014 | COMMERCIAL - TI | 07/22/2014 | COMPLETED |
07/22/2014 | RESUBMITTAL - TI ALL | 08/01/2014 | COMPLETED |
08/01/2014 | RESUBMITTAL - TI ALL | 08/13/2014 | COMPLETED |
08/13/2014 | RESUBMITTAL | 10/15/2014 | COMPLETED |
10/15/2014 | REVISION - - 1ST | 06/09/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM03839
Permit Status: C of o
Permit Description: PALO VERDE BEHAVIORAL HEALTH BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/20/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM03839
Permit Description: PALO VERDE BEHAVIORAL HEALTH BUILDING
Total Completed Inspections - 48
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/18/2014 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | LETTER FOR SDR 35 FROM M.LO TEMPIO SEWER TEST OK |
09/18/2014 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
11/18/2014 | EXCAVATION/LAYOUT REBAR & ZON | BBENEDOI | Approved | IVRS - Inspection :* |
11/26/2014 | REINFORCED MASONRY PRE-GROUT | RCANCINO | Approved | OK TO GROUT SOUTH WALL EAST END 1ST & SECOND LIFT OF BLDG |
11/26/2014 | STEM WALL/RETAINING WALL | RCANCINO | Approved | CENTRAL & EASTWALL OK TO POOR |
11/26/2014 | REINFORCED MASONRY PRE-GROUT | RCANCINO | Approved | IVRS - Inspection :* |
11/26/2014 | STEM WALL/RETAINING WALL | RCANCINO | Approved | IVRS - Inspection :* |
12/01/2014 | PLUMBING - ROUGH, SOIL | BBENEDOI | Approved | IVRS - Inspection :* |
12/08/2014 | ELECTRIC - INTERMEDIATE | JMILITELLO | Approved | OK TO COVER ELEC UNDERGROUND WITHIN THE STRUCTURE |
12/08/2014 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
12/09/2014 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | EXAM 007 UNDERGROUND OK |
12/09/2014 | PLUMBING - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
12/10/2014 | BUILDING PRE-SLAB | JMILITELLO | Approved | OK TO POUR SLAB |
12/10/2014 | BUILDING PRE-SLAB | JMILITEL | Approved | IVRS - Inspection :* |
01/15/2015 | EXT METAL CLIPS/EXT SHEATHING | BBENEDOI | Approved | IVRS - Inspection :* |
02/05/2015 | ROOF NAILING | BBENEDOI | Approved | IVRS - Inspection :* |
03/09/2015 | PLUMBING - GAS PRESSURE TEST | JMILITEL | Approved | IVRS - Inspection :* |
03/09/2015 | STUCCO MESH | JMILITEL | Approved | IVRS - Inspection :* |
03/26/2015 | MECHANICAL - INTERMEDIATE | BBENEDOI | Approved | IVRS - Inspection :* |
03/27/2015 | PLUMBING - ROOF DRAINS | BBENEDOI | Approved | IVRS - Inspection :* |
04/06/2015 | SHEET ROCK NAILING | BBENEDOI | Approved | IVRS - Inspection :* |
04/08/2015 | PLUMBING - YARD WTR LINE/TEST | BBENEDOI | Approved | IVRS - Inspection :* |
04/08/2015 | FRAMING | BBENEDOI | Approved | IVRS - Inspection :* |
05/08/2015 | MECHANICAL - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
05/08/2015 | PLUMBING - ABOVE CEILING | BBENEDOI | Approved | IVRS - Inspection :* |
05/08/2015 | ELECTRIC - ABOVE CEILING | BBENEDOI | Approved | IVRS - Inspection :* |
05/14/2015 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | NEW ADDITION COMPLETE |
05/14/2015 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | IVRS - Inspection :* |
05/22/2015 | BUILDING - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
05/22/2015 | ELECTRIC - OUTDOOR LIGHTING | BBENEDOI | Approved | IVRS - Inspection :* |
05/22/2015 | BUILDING ABOVE CEILING | BBENEDOI | Approved | IVRS - Inspection :* |
05/22/2015 | ELECTRIC - PROGRESS | BBENEDOI | Approved | IVRS - Inspection :* |
05/22/2015 | PLUMBING - GAS PRESS TEST FNL | BBENEDOI | Approved | IVRS - Inspection :* |
05/26/2015 | MECHANICAL - ABOVE CEILING | BBENEDOI | Approved | IVRS - Inspection :* |
05/28/2015 | PLUMBING - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
06/04/2015 | ELECTRIC - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
06/04/2015 | LANDSCAPE - FINAL | RLEDONNE | Approved | |
06/04/2015 | NPPO - FINAL | RLEDONNE | Approved | |
06/04/2015 | SIGN - FINAL | RLEDONNE | Approved | |
06/05/2015 | ZONING - FINAL | RLEDONNE | Approved | |
06/05/2015 | ENGINEERING - FINAL | RLEDONNE | Approved | |
06/15/2015 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
06/15/2015 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
06/15/2015 | FIRE - FINAL | CSCHULTZ | Approved | |
06/15/2015 | BUILDING - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
06/15/2015 | BUILDING - FINAL | BBENEDOI | Approved | IVRS - Inspection :* |
06/16/2015 | RIGHT OF WAY - FINAL | DRUSSELL | Approved | |
06/16/2015 | U VALUE FOR WINDOW | AROMERO4 | Approved | PER FINAL |